Create a Microsoft Project Master Schedule with Linked Subprojects
Question details
Create a master schedule that includes detailed subprojects and keeps relevant milestones and cross-file dependencies synchronized.

- Product
- Microsoft Project desktop
- Device & OS
- not provided
- Scenario
- A master schedule tracks high-level milestones and baselines while several subprojects are updated weekly.
- Observed behavior
- The user wants subproject changes and linked milestone dates to be reflected in the master schedule when the files are available and updated.
Confirm that you can access the master file and each subproject from a stable shared location, with permission to open and save them. Identify the milestones and detailed tasks that need cross-project dependencies.
Insert linked subprojects and connect their tasks
Use a consolidated master project to view subproject schedules and create dependencies between tasks in different files.
Linked subprojects remain separate files. Changes can be reflected in the master when the files are accessible and links are updated, but synchronization depends on file paths, permissions, and link settings.
Where practical, link detailed tasks or milestones rather than summary tasks, because dependencies on summary tasks can make schedules harder to interpret.
In Microsoft Project desktop, select File > New > Blank Project, then use File > Save As to save the master schedule in an accessible location.
In the Gantt Chart view, select the row where a subproject should appear. Choose Project > Subproject, select the project file, make sure Link to project is selected, and select Insert. Repeat for the other subprojects.
Expand the inserted subprojects in the Gantt Chart. Select the predecessor task or milestone and the successor task or milestone, then choose Task > Link Tasks. Check the resulting dependency in the successor's Predecessors field.
When the schedule is approved, choose Project > Set Baseline > Set Baseline and select the appropriate scope. Review baseline settings in each subproject as needed; a baseline is a saved snapshot, not a live link.
Save the master and any changed subprojects. After a weekly update, reopen the master, respond to any link-update prompts, and check the linked milestones and predecessor relationships in the Gantt Chart.

Track Project Milestones in WPS Spreadsheets
WPS Office is a free, lightweight alternative for maintaining a milestone tracker in a familiar spreadsheet interface. Its Microsoft Excel format compatibility makes it easy to migrate existing trackers, though it does not replace Microsoft Project's linked subprojects or scheduling dependencies.

Frequently Asked Questions
Do I need Project Server to create a master schedule?
No. In Microsoft Project desktop, you can use Project > Subproject to insert linked project files. Project Server or another centralized service can help with enterprise collaboration but is not required for a basic master schedule.
Why is a subproject change missing from the master schedule?
Check that the updated subproject was saved and that the master can access it at its linked path. Reopen the master and respond to any link-update prompts, then verify file permissions and link settings.
Will a baseline update automatically when a subproject changes?
No. A baseline is a snapshot of the schedule at the time it is set. Review it through Project > Set Baseline, and set or change it only when appropriate for your reporting process.
Can I link a milestone in one subproject to a task in another?
Yes. Expand both subprojects in the master Gantt Chart, select the predecessor and successor in order, and choose Task > Link Tasks. Confirm the dependency in the successor's Predecessors field.