Report Resources Across Microsoft Project Master and Subprojects
Question details
Create a summary of resources and their time across a master project and its subprojects without listing individual tasks.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A master project contains linked subprojects that use a shared resource pool, and the user wants a project-by-resource summary.
- Observed behavior
- The desired report groups resources under each project and rolls up their time to project and master totals.
Open the master project with its subprojects and resource pool available, and confirm whether you need elapsed duration or resource work totals. Avoid renaming, moving, or overwriting files in the linked structure; if you make a backup, close the files and preserve the complete set and its link relationships.
Review cross-project assignments in Resource Usage
Use this view to inspect resources and their assignments across the open master and subprojects before building a summary.
Resource Usage is resource-first and normally includes task-level assignment rows. It may not produce the requested project-first summary without additional grouping or an export.
Work is the effort assigned to resources; duration is the elapsed working time of a task or project. Adding resource days gives a work total, not necessarily the project's scheduled duration.
Open the master project and select View > Resource Usage. Expand the relevant subprojects and resources to inspect their assignments.
Right-click a column heading, choose Insert Column, and select Project if it is available. Check whether the project values identify the assignment rows you need.
Use Insert Column to add Work, then compare the resource and assignment values. Adjust the timescale in the Resource Usage view if you need to inspect work by day or week.
On the View tab, open Group by and choose More Groups or a new custom group if available. Test a project-first grouping and verify its totals; grouping options can vary by Project version and view.

Create a static master for a separate reporting view
Use a static master when you want inserted project data without keeping the inserted subproject links in the new master.
Export assignment data for a project-by-resource summary
Use a spreadsheet when Project's views cannot provide the requested task-free layout.
Summarize Project Resource Work in WPS Spreadsheets
If a spreadsheet is acceptable, export assignment data from Microsoft Project to an Excel workbook, then use WPS Spreadsheets to group resource work by project. WPS does not replace the linked Project files or fix their links.
- 1. Export from Project: In Microsoft Project, use File > Save As and the Export Wizard to create an Excel workbook containing assignment resource names and work. Include or add a project identifier for each row.
- 2. Open the workbook: In WPS Spreadsheets, choose Open and select the exported Excel workbook. Check that the project, resource, and work columns are populated.
- 3. Insert a PivotTable: Select the exported data and choose Insert > PivotTable. Place Project and then Resource in the row fields, and add Work to the values as a sum.
- 4. Verify and save: Compare the project and grand totals with Microsoft Project, then choose File > Save As to save the summary as an XLSX workbook.

Frequently Asked Questions
Can Resource Usage show resources from all subprojects?
Open the master with its linked subprojects available, then select View > Resource Usage. Expand resources to inspect their assignments and check the project information shown for each row.
Is the sum of resource days the same as project duration?
Not necessarily. Resource work is effort assigned to people, while project duration is scheduled elapsed working time. Concurrent assignments can make the two totals different.
What happens when I clear Link to Project?
In the Insert Project dialog, clearing Link to Project inserts an unlinked copy into the master. Later changes to the original subproject do not automatically update that copy.
How can I report resources without showing tasks?
Try a custom grouping from View > Group by in Project. If it does not provide the required layout, export assignment data and create a PivotTable with Project and Resource as rows and Work as the value.
Can WPS Spreadsheets open the Project file directly?
For this workflow, first export the Project data to an Excel workbook using File > Save As and the Export Wizard. Then open the workbook in WPS Spreadsheets; the spreadsheet does not maintain the original Project links.