Create a Resource Usage Report in Microsoft Project 2013
Question details
Create a time-phased report showing resources, tasks, work, and usage data in Microsoft Project 2013.

- Product
- Microsoft Project 2013
- Device & OS
- not provided
- Scenario
- The user wants a report similar to the Resource Usage workload report available in Project 2010.
- Observed behavior
- The older Resource Usage workload report is not available in Project 2013.
Open the project in Microsoft Project 2013 and confirm that resources are assigned to tasks with work data. You will also need Microsoft Excel to create and customize the Visual Report.
Create an Assignment Usage Visual Report in Excel
Use a custom Visual Report and PivotTable to show resource assignments and work by time period.
Project 2013 cannot exactly reproduce the Resource Usage report from Project 2010, but an Assignment Usage Visual Report can provide similar time-phased information.
In Project 2013, open your project and select Report > Visual Reports.
In the Visual Reports dialog, click New Template, select Excel and Assignment Usage, and use Field Picker to add any extra fields you need. Click OK to create the report workbook.
In the Visual Reports dialog, use Select Level of Usage Data to Include in the Report to choose a time level such as Weekly. Select the template and click View if needed to generate the report.
In Excel, use the PivotTable field list to add Resources and Tasks to Rows, Time to Columns, and Work to Values.
Expand the Time column to the desired level, then expand the project and summary tasks in the PivotTable to show tasks for each resource.
If the report meets your needs, save the workbook as a template in the default Templates folder so you can reuse it.

Review Project report workbooks with WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface and Microsoft Office format compatibility, making it easy to move between office suites. Use WPS Spreadsheets to open and review an Excel report workbook; creating the Project Visual Report still requires Microsoft Project and Excel.

Frequently Asked Questions
Where is the Resource Usage report in Project 2013?
The older Project 2010 workload report is not available in the same form. In Project 2013, go to Report > Visual Reports and create an Assignment Usage report instead.
How do I show weekly work in the report?
In the Visual Reports dialog, choose Weekly from Select Level of Usage Data to Include in the Report. In the resulting Excel PivotTable, expand Time to show the weekly level.
Which PivotTable fields show tasks for each resource?
Add Resources and Tasks to the Rows area, Time to Columns, and Work to Values. Expand the project and summary tasks to display the assignments.
Can the Visual Report exactly match the Project 2010 report?
No. A customized Excel PivotTable can provide similar resource, task, and time-phased work data, but it cannot exactly duplicate the older report.