Report Actual Hours by Year and Resource in Microsoft Project 2013
Question details
Create an exportable report of actual project hours by calendar year and resource in Microsoft Project 2013.

- Product
- Microsoft Project 2013
- Device & OS
- not provided
- Scenario
- The user wants an automated view of actual work, organized by resource and calendar year, for further analysis.
- Observed behavior
- The desired report shows each resource's actual work hours for each calendar year and can be analyzed in Excel.
Open the project in Microsoft Project 2013 and check that actual work has been recorded for the relevant resource assignments. For an Excel Visual Report, make sure a compatible desktop version of Excel is installed.
View actual work by year in Resource Usage
Use this view to review yearly actual hours for each resource directly in Project.
Open the project, select the View tab, and choose Resource Usage.
Right-click the timephased grid on the right and select Actual Work. If needed, clear Work from the same menu to focus on actuals.
Right-click the timescale above the grid and choose Timescale. Set the displayed tier's Units to Years, then click OK.
Use the resource rows to review the actual work shown under each year. Expand a resource row to inspect its individual assignments.
Select the relevant cells in the usage grid, copy them, and paste them into an Excel worksheet. Check the pasted labels and values before analyzing them.

Create an Excel Visual Report for resource actuals
Use a Visual Report when you want a timephased Excel PivotTable that can be rearranged for analysis.
Analyze exported project hours in WPS Spreadsheet
WPS Office is a free, lightweight alternative with a familiar interface and Microsoft Office format compatibility, making it easy to move exported project data into a spreadsheet for analysis. It does not replace Microsoft Project's scheduling or Visual Reports features.

Frequently Asked Questions
Why does my report show work instead of actual work?
Work and Actual Work are different fields. In View > Resource Usage, right-click the timephased grid and select Actual Work to display the recorded actual hours.
How do I see individual assignments under a resource?
In the Resource Usage view, expand the resource row to show its assignments. The timephased grid shows the selected work details for those rows.
Does the Excel report update automatically when Project data changes?
A copied range is a snapshot. For current figures, copy the Resource Usage data again or generate a new report through Report > Visual Reports.
Can I open the exported Excel workbook in WPS Office?
Yes. Open the saved XLSX file in WPS Spreadsheet to review the exported data. Check any PivotTable features you need, since compatibility can vary.




