Create a customizable report of resource availability and work over time.

Create a Resource Availability Report in Microsoft Project 2016
Product
Microsoft Project 2016 and Microsoft Excel
Device & OS
not provided
Scenario
A project manager wants to compare resource availability, scheduled work, and remaining availability by week.
Observed behavior
The desired report shows time-phased resource data that can help identify overallocated and underutilized resources.
Before you start

Open the project in Microsoft Project 2016 and confirm that resource assignments, work estimates, and resource calendars are up to date. Make sure Excel is available for creating the Visual Report.

Solution 1Recommended

Create an Excel Visual Report from Resource Usage data

Use a PivotTable-based Visual Report to compare weekly availability and work by resource.

1
Open Visual Reports

In Microsoft Project, open the project and select Report > Visual Reports.

2
Create a template

Select New Template, choose Excel as the application, and select Resource Usage as the data type.

3
Choose the report fields

Use the field picker to include Work Availability, Work, and Remaining Availability, then create the template in Excel.

4
Arrange the PivotTable

In Excel's PivotTable Fields pane, place Resources in Rows, Weekly Calendar in Columns, and Work Availability, Work, and Remaining Availability in Values, in that order.

5
Expand the time dimension

Use the expand controls in the PivotTable's calendar headings to show the required weekly detail.

6
Save the template

In Excel, select File > Save As and choose Excel Template (*.xltx) to save the customized workbook for reuse.

Create an Excel Visual Report from Resource Usage data
Report time span and headings: The report covers the time span of the open project. Weekly headings may show labels such as Week 14 rather than actual dates. Compare Work with Work Availability to identify potential overallocation; remaining availability can help reveal unused capacity.
Free Microsoft Office alternative

Review Excel resource reports with WPS Office

WPS Office is a free, lightweight alternative with a familiar interface for working with Office files. Open an exported resource report in WPS Spreadsheet for further review, while using Microsoft Project to create the Visual Report.

Review exported resource availability and work data in a spreadsheet.Compatible with Microsoft Excel formats, including XLSX.Familiar spreadsheet interface makes moving from Office easier.Free and lightweight for everyday document work.
QA img-9

Frequently Asked Questions

How can I see resource availability without exporting to Excel?

Select View > Resource Usage in Microsoft Project, then right-click the timescaled details area to add availability and work fields.

How do I identify overallocated resources in the report?

Compare Work with Work Availability for each resource and period. Work above available capacity can indicate overallocation.

Why does the report show week numbers instead of dates?

The Weekly Calendar dimension can label columns with week numbers, such as Week 14. Expand the calendar dimension in the PivotTable to see the available time detail.

Does the Visual Report include dates outside the project?

The report displays the time span covered by the open project. Check the project schedule in Microsoft Project if you need a different reporting period.