Question details
The user needs to generate a resource report that covers a specific time period using date-range filtering.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Filtering resource data in a project or resource pool file to view scheduled work between specific start and end dates.
- Observed behavior
- The user requires clear steps to isolate and display resource usage for a defined period, navigating the built-in Date Range filter limitations and exploring advanced reporting methods.
Ensure your project plan is up to date, all resources are properly assigned to tasks, and any linked resource pool files are fully synchronized.
Use the Resource Usage View with Date Range Filter
Apply the built-in Date Range filter to quickly identify resources scheduled to work within your specified period.
This method is highly effective for quickly viewing resource allocations in shared and resource-pool files. However, note that while the filter identifies resources working during the specified dates, it does not hide the work those resources perform outside of the selected period.
Navigate to the 'View' tab on the ribbon and click on 'Resource Usage'.
Click the 'Filter' drop-down menu in the Data group and select 'Date Range...'.
Enter your desired start and end dates in the prompt dialog boxes to apply the filter.
Right-click anywhere on the timescaled grid on the right side of the view to select and display necessary fields, such as 'Work' or 'Cumulative Work'.

Use Visual Reports to Export Data to Excel
Export your project data into an Excel pivot table for detailed, strictly bounded period-based reporting.
Analyze Exported Project Reports with WPS Office
When you export Microsoft Project resource reports for deep analysis, WPS Office provides a lightweight, highly compatible, and completely free alternative to Microsoft Excel for editing and formatting your data.
- 1. Download WPS Office: Install the free WPS Office suite on your computer.
- 2. Open WPS Spreadsheet: Launch the application and select the Spreadsheet module.
- 3. Import Your Report: Open the .xlsx file exported from Microsoft Project's Visual Reports to customize your date-range data.

Frequently Asked Questions
Why does my date range filter show work outside the specified dates?
The Date Range filter in the Resource Usage view identifies resources that have any work scheduled within your specified dates. It filters the resource list, but it does not restrict the timescaled grid from displaying work those resources perform outside the filtered period.
Can I add multiple conditions to the Date Range filter in MS Project?
Microsoft Project does not support nested filters directly, but you can edit the existing Date Range filter. Go to 'More Filters', select the Date Range filter, click 'Edit', and add custom 'And/Or' conditions to refine your reporting.
How do I find the Cumulative Work field in the Resource Usage view?
To view Cumulative Work, right-click the timescaled grid area on the right side of the screen. In the context menu that appears, select 'Cumulative Work' to display it alongside your standard work hours.
What is the best way to print a resource report for a specific month only?
For precise period-based reporting without extraneous data, it is recommended to use the Visual Reports feature to export your data to Excel. Once in Excel, you can strictly filter the PivotTable to the exact month and print a clean report.