Export Project 2013 Resource Usage Data to Excel

Algirdas JasaitisAlgirdas Jasaitis Nov 27, 2026 868 views

Question details

Export resource usage data from Microsoft Project 2013 to Excel, including tasks, resources, monthly work, and the Text1 custom field.

Export Project 2013 Resource Usage Data to Excel
Product
Microsoft Project 2013 and Microsoft Excel
Device & OS
not provided
Scenario
The user wants an Excel representation of the Resource Usage view with task outlines and custom field data.
Observed behavior
Project 2013 does not directly export the Resource Usage view to Excel in the same raw format shown on screen.
Before you start

Open the project in Project 2013 and verify that Task Text1 contains the information you need. Make sure Excel is available to create and edit the Visual Report.

Solution 1Recommended

Create an Assignment Usage Visual Report in Excel

Use a custom Visual Report to bring resource assignments, time-phased work, and Task Text1 into Excel.

This method produces an Excel PivotTable rather than an exact copy of the Resource Usage view. You can adjust the layout and convert the OLAP PivotTable to formulas, but further formatting may be needed.

1
Open Visual Reports

In Project 2013, open the project and select Report > Visual Reports.

2
Create a template

Select New Template, choose Excel, and select Assignment Usage as the data type. Use the Field Picker to add Task Text1 and any other required custom fields.

3
Choose the time level

In the Visual Reports dialog, choose Months as the level of usage data to include, then create or view the report in Excel.

4
Arrange the report fields

In Excel's PivotTable Fields pane, add Resources and Tasks to Rows, Time to Columns, and Work to Values.

5
Show the custom field

Right-click a task in the PivotTable, select Show Properties in Report, and choose Text1.

6
Convert the PivotTable if needed

Select the PivotTable and choose Analyze > OLAP Tools > Convert to Formulas to replace the OLAP PivotTable structure with worksheet formulas.

Create an Assignment Usage Visual Report in Excel
The result is not an exact replica: Convert to Formulas changes the PivotTable into formulas; it does not automatically create a flat, static table or reproduce every detail of Project's Resource Usage view.
Free Microsoft Office alternative

Review exported resource usage data in WPS Office

WPS Office is a free, lightweight Office alternative with a familiar interface and Excel format compatibility, making it easier to move exported worksheets into a different suite. Create the Project Visual Report and perform any OLAP conversion in Microsoft Excel first; WPS Office does not fix Project 2013's export limitation.

Review exported resource and work data in WPS SpreadsheetsCompatible with Microsoft Excel XLSX and XLS formatsFree, lightweight Office alternativeFamiliar spreadsheet interface for easier migration
microsoft office alternative - wps office

Frequently Asked Questions

Can Project 2013 export an exact copy of the Resource Usage view?

Project 2013 does not directly export the view to Excel in the same raw on-screen format. An Assignment Usage Visual Report is an alternative, but its PivotTable layout may need additional formatting.

How do I include Task Text1 in the report?

When creating the Visual Report template, add Task Text1 with the Field Picker. In Excel, right-click a task in the PivotTable, select Show Properties in Report, and choose Text1.

How can I show work by month?

In Project's Visual Reports dialog, select Months as the usage data level. In Excel, place Time in the PivotTable Columns area and Work in Values.

Does Convert to Formulas create a static table?

No. In Excel, Analyze > OLAP Tools > Convert to Formulas replaces the OLAP PivotTable structure with worksheet formulas; it does not automatically turn the report into static values.