Export Project 2013 Resource Usage Data to Excel
Question details
Export resource usage data from Microsoft Project 2013 to Excel, including tasks, resources, monthly work, and the Text1 custom field.

- Product
- Microsoft Project 2013 and Microsoft Excel
- Device & OS
- not provided
- Scenario
- The user wants an Excel representation of the Resource Usage view with task outlines and custom field data.
- Observed behavior
- Project 2013 does not directly export the Resource Usage view to Excel in the same raw format shown on screen.
Open the project in Project 2013 and verify that Task Text1 contains the information you need. Make sure Excel is available to create and edit the Visual Report.
Create an Assignment Usage Visual Report in Excel
Use a custom Visual Report to bring resource assignments, time-phased work, and Task Text1 into Excel.
This method produces an Excel PivotTable rather than an exact copy of the Resource Usage view. You can adjust the layout and convert the OLAP PivotTable to formulas, but further formatting may be needed.
In Project 2013, open the project and select Report > Visual Reports.
Select New Template, choose Excel, and select Assignment Usage as the data type. Use the Field Picker to add Task Text1 and any other required custom fields.
In the Visual Reports dialog, choose Months as the level of usage data to include, then create or view the report in Excel.
In Excel's PivotTable Fields pane, add Resources and Tasks to Rows, Time to Columns, and Work to Values.
Right-click a task in the PivotTable, select Show Properties in Report, and choose Text1.
Select the PivotTable and choose Analyze > OLAP Tools > Convert to Formulas to replace the OLAP PivotTable structure with worksheet formulas.

Review exported resource usage data in WPS Office
WPS Office is a free, lightweight Office alternative with a familiar interface and Excel format compatibility, making it easier to move exported worksheets into a different suite. Create the Project Visual Report and perform any OLAP conversion in Microsoft Excel first; WPS Office does not fix Project 2013's export limitation.

Frequently Asked Questions
Can Project 2013 export an exact copy of the Resource Usage view?
Project 2013 does not directly export the view to Excel in the same raw on-screen format. An Assignment Usage Visual Report is an alternative, but its PivotTable layout may need additional formatting.
How do I include Task Text1 in the report?
When creating the Visual Report template, add Task Text1 with the Field Picker. In Excel, right-click a task in the PivotTable, select Show Properties in Report, and choose Text1.
How can I show work by month?
In Project's Visual Reports dialog, select Months as the usage data level. In Excel, place Time in the PivotTable Columns area and Work in Values.
Does Convert to Formulas create a static table?
No. In Excel, Analyze > OLAP Tools > Convert to Formulas replaces the OLAP PivotTable structure with worksheet formulas; it does not automatically turn the report into static values.