Manage Linked Subprojects and Resource Names in Microsoft Project 2013

Amos GikundaAmos Gikunda Nov 25, 2026 869 views

Question details

Standardize employee resource names across Project 2013 subprojects without damaging the linked master schedule.

Manage Linked Subprojects and Resource Names in Microsoft Project 2013
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
A master schedule contains linked subprojects with thousands of tasks, and the files are being moved to a common drive accessed across a WAN.
Observed behavior
Resource names are inconsistent across project files, and the user wants to reduce manual renaming while preserving links, assignments, and baselined schedules.
Before you start

Identify the master file, subprojects, resource pool, cross-project dependencies, and current file locations. Record which resource names should change and whether similarly named records represent the same person; make copies of all related files and test changes in an isolated set with links checked before editing production files.

Solution 1Recommended

Standardize employee names in the resource pool and projects

Use this approach for a manageable number of name changes, especially when projects share a resource pool.

A resource pool is a separate file of resources shared by projects; it is not a bulk-renaming tool. If the pool is only used as a template, each project may have its own resource records that need updating.

Renaming a resource record does not automatically merge duplicate records. Check assignments and confirm that each record represents the intended employee before changing it.

1
Check the sharing setup

Open a subproject and select Resource > Resource Pool > Share Resources to check whether it uses a shared pool or its own resources.

2
Review resource records

Open the pool or project file and select View > Resource Sheet. Compare the Resource Name entries with your approved employee-name list.

3
Update names consistently

In Resource Sheet, edit the Resource Name cells for the correct employee records. Repeat in project files that contain separate resource records, coordinating access to the shared pool as needed.

4
Verify assignments and links

Review affected task assignments and cross-project links in the test files, then save and reopen them to confirm the names and connections remain correct.

Standardize employee names in the resource pool and projects
Keep named assignments: Generic resources such as Engineer can simplify planning when individuals are not required, but they do not replace named employee assignments.
Free Microsoft Office alternative

Use WPS Office for Resource Lists and Project Documentation

WPS Office is a free, lightweight alternative for everyday office work, with a familiar interface and Microsoft Office format compatibility for a smooth move between applications. Use WPS Spreadsheets to prepare a resource-name mapping and WPS Writer to document the migration plan; linked Microsoft Project schedules still require Project-compatible tools.

Prepare and review employee-name mapping tables in WPS SpreadsheetsOpen and edit Microsoft Excel XLSX and Word DOCX filesUse a familiar interface for everyday office tasksKeep migration notes and resource lists together in a lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Can a resource pool rename employees in every project automatically?

A resource pool stores resources shared by projects, but it is not a bulk-renaming tool. Check Resource > Resource Pool > Share Resources in each project; projects with separate resource records may need their own updates.

Will renaming two resource records merge their assignments?

No. Giving records the same name does not automatically merge them. Review the records and their task assignments separately before deciding how to consolidate duplicates.

Can I move a linked subproject to a common drive?

Yes, but first document its master, external dependencies, and resource-pool links. Test unlinking and relinking in an isolated set, then reopen the master and check all references after the move.

Is a WAN a reliable way to maintain linked Project files?

Network interruptions can make linked-file operations risky. Coordinate changes through one maintainer and consider an enterprise scheduling service such as Project Server or Project Online if appropriate and available for your organization.

Can WPS Office repair a Microsoft Project master schedule?

No. WPS Office can help prepare resource-name lists and documentation, but it does not repair Microsoft Project links or update assignments in linked Project schedules.