Question details

The user needs current task, cost, and date information from linked subprojects in a Project 2013 master file.

Refresh Collapsed Subprojects in a Microsoft Project 2013 Master File
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
A master project contains linked subprojects that are collapsed when the master is opened or reviewed.
Observed behavior
Task, cost, or date information may not refresh until the linked subprojects are opened or expanded.
Before you start

Confirm that the subprojects are linked and that their source files are accessible. Identify a changed task, cost, or date in a source file so you can check whether the master displays the latest information.

Solution 1Recommended

Expand linked subprojects before reviewing the master

Use this approach to load the linked subprojects and check their current information in the master file.

A collapsed linked subproject may not show refreshed information until it is opened or expanded. This behavior is expected; loading every subproject automatically can take time and may increase the risk of corruption.

1
Open the master project

In Microsoft Project 2013, select File > Open and open the master project.

2
Expand each subproject

In the task table, select the expand control beside each collapsed subproject summary task. If necessary, open the linked subproject file directly.

3
Check and save the master

Compare the known changed task, cost, or date with the source file. Use File > Save to save the master with the subprojects expanded.

4
Verify the next refresh

Reopen the master from File > Open and check the same information. If it is not current, expand or open the affected subproject again.

Expand linked subprojects before reviewing the master
Refresh is not guaranteed: Saving the master with subprojects expanded can help with review, but verify the values after reopening rather than assuming every linked file has refreshed.
Free Microsoft Office alternative

Review exported project reports in WPS Office

WPS Office is a free, lightweight alternative for everyday office work, with a familiar interface and support for common Microsoft Office formats. Export project data to a spreadsheet for reporting in WPS; WPS does not refresh Microsoft Project linked subprojects.

Review and organize exported project data in WPS SpreadsheetsWork with Microsoft Excel XLSX, Word DOCX, and PowerPoint PPTX filesUse a familiar office interface for an easier transitionCreate and share reports with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does a collapsed subproject show outdated information?

In a linked master project, a collapsed subproject may not be loaded and refreshed until you expand its summary task or open its source file. Loading every subproject automatically can be slow and may increase corruption risk.

Will saving the master with subprojects expanded guarantee an update?

No. Save the master with the subprojects expanded, then reopen it and compare a known changed value with the source file. Expand or open the affected subproject if the value is still outdated.

How do I prevent a reporting snapshot from linking to source projects?

In a separate blank project, select Project > Subproject and clear Link to project in the Insert Project dialog before inserting each source file. Rebuild the snapshot when you need newer data.

Can a macro automate this process?

A VBA macro can be developed to open subproject files or build a reporting snapshot. Test it on representative files and verify the resulting task, cost, and date values.

Can WPS Office refresh linked Microsoft Project subprojects?

No. Use Microsoft Project to open and refresh the linked subprojects. You can export project data to an Excel spreadsheet and use WPS Spreadsheets to review or prepare reports.