Show the Critical Path for Selected Milestones in Microsoft Project
Question details
The user wants to display the critical path affecting selected milestones after entering milestone deadlines.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project plan contains selected milestones with deadlines, and the user wants to identify the tasks that drive them.
- Observed behavior
- Deadlines have been entered for the milestones, but the user needs to know how to display the relevant critical tasks.
Open the project in Gantt Chart view and check that the milestones have the intended deadlines. Verify that the relevant tasks are linked and use automatic scheduling where appropriate.
Link Tasks and Highlight the Critical Path
Use Project's calculated critical tasks to see which activities affect the project finish or have critical deadline slack.
Microsoft Project calculates critical tasks from the schedule rather than creating a separate critical path from a manual selection. A deadline can affect a task's slack and whether it is marked critical.
In Gantt Chart view, review the Predecessors column for the tasks leading to each milestone. Enter the appropriate predecessor task IDs or select tasks and choose Task > Link Tasks.
Add or review the Deadline column in the task table. Enter the intended deadline for each milestone; setting it to the current finish date does not by itself create a separate milestone path.
Press F9 to recalculate the project after changing dependencies or deadlines. Check the milestone finish dates and correct any unintended links or constraints.
Open the Gantt Chart Format tab and select Critical Tasks. Project highlights tasks it calculates as critical in the Gantt chart.
On the View tab, use the Critical filter to show critical tasks only. Clear the filter when you need to see the full schedule again.

Trace the Driving Tasks for a Selected Milestone
Use task-path highlighting to focus on the chain that drives a particular milestone.
Track Project Milestones in WPS Spreadsheets
For a lightweight, free alternative to Office spreadsheets, use WPS Spreadsheets to organize milestone dates and task lists in a familiar interface. Open compatible Excel files to move spreadsheet-based plans into WPS; Microsoft Project is still needed for its calculated critical-path features.

Frequently Asked Questions
Does adding a deadline automatically create a separate critical path?
No. The Deadline field can affect slack and critical-task calculations, but Project calculates the schedule from the task network rather than creating a separate path for each selected milestone.
How do I show only critical tasks?
In Gantt Chart view, open the View tab and apply the Critical filter. This filters critical tasks across the project, not just those related to one milestone.
How can I see which tasks drive a milestone?
Select the milestone in Gantt Chart view, then choose Gantt Chart Format > Task Path > Driving Predecessors. Compare that path with critical-task highlighting to distinguish driving tasks from tasks Project marks as critical.
Why is a driving predecessor not marked critical?
A task can drive a milestone's scheduled date but still have slack relative to the project finish or an applicable deadline. Review its links and deadline, then check the Critical Tasks display.