Question details

The user wants a renamed Project Summary Task to retain its name after the project file is reopened.

Microsoft Project 2013 Project Summary Task Name Reverts After Reopening
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
The user renames the Project Summary Task, saves the project, and reopens the file.
Observed behavior
The Project Summary Task name changes back to the project file name after reopening.
Before you start

Open the affected project in Microsoft Project 2013 and make sure the Project Summary Task is visible. Note the name you want to use so you can check whether it persists after reopening.

Solution 1Recommended

Check the Project Summary Task Name and Available Updates

Use these steps to confirm the behavior and check for available Microsoft updates. The name reverting is a known Project 2013 bug with no reliable workaround.

1
Show the summary task

In the Gantt Chart view, open the Format tab and select the Project Summary Task checkbox.

2
Rename and save

Edit the name in the Project Summary Task row, then select File > Save.

3
Reopen the project

Close the project, reopen it from File > Open, and check whether the summary task name has reverted to the file name.

4
Check for updates

Select File > Account > Update Options > Update Now if that option is available. If it is not, check Windows Update or contact your administrator about updates for your installation.

Check the Project Summary Task Name and Available Updates
No reliable workaround: The name reverting after reopening is a known Microsoft Project 2013 bug. Installing available updates is worth checking, but it is not a guaranteed fix.
Free Microsoft Office alternative

Track Project Tasks in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for everyday office work. Use WPS Spreadsheets to maintain a simple task list and move compatible spreadsheet files between office suites. It does not fix the Microsoft Project 2013 bug.

Create a simple project task list with a name you chooseOpen and save Microsoft Excel XLSX files for spreadsheet compatibilityUse familiar spreadsheet tools to ease migration from Microsoft OfficeWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does my Project Summary Task name change back?

In Microsoft Project 2013, this is a known bug: the name can revert to the project file name after you save, close, and reopen the file.

How do I display the Project Summary Task?

In the Gantt Chart view, select the Format tab and check Project Summary Task.

Is there a reliable workaround for the name reverting?

No reliable workaround is known for this Project 2013 behavior. You can check for available updates, but an update is not guaranteed to fix it.

Can WPS Office fix the Microsoft Project bug?

No. WPS Office cannot fix Microsoft Project itself. WPS Spreadsheets can be used separately to maintain a simple project task list.