Fix Custom Fields Not Synchronizing in Subproject Summary Tasks in MS Project
Question details
Custom fields entered on a subproject summary task fail to synchronize with the corresponding summary line displayed in a master project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Working with dynamic master projects and subprojects to track custom field data across multiple project levels.
- Observed behavior
- The custom fields added to a subproject's Project Summary Task do not appear or sync on the master-project level summary line.
Verify whether your master project is dynamic (containing links to subprojects) or static, as this determines how summary tasks and custom fields behave across files.
Reconfigure Data Consolidation and Master Project Reporting
Adjust your data consolidation approach by understanding that dynamic master projects use pointers rather than perfectly synchronized summary tasks.
In a dynamic master project, the master file only contains pointers or links to the subproject files, rather than completely incorporating the subprojects. The summary line you see in the master project is actually part of the master itself, not the subproject.
Because they are entirely separate tasks, custom fields entered at the subproject level's Project Summary Task will not automatically carry over or synchronize to the master project summary line.
Open the master project and look at the ID fields. If the ID field starts over for each subproject, it confirms your subprojects are linked as pointers and will not natively sync custom summary fields.
Instead of entering the custom field data directly on the subproject's Project Summary Task expecting it to roll up, manually input the required custom field data directly onto the master project's summary line.
For automated data consolidation across multiple projects, consider writing a VBA macro or using Project Server/Project Online reporting features, as default dynamic links do not support syncing these fields natively.

Manage Projects Efficiently with WPS Office
While Microsoft Project has specific constraints with subprojects and dynamic master files, many project management and data consolidation tasks can be simplified using robust spreadsheet tools. WPS Office provides a free, lightweight, and highly compatible alternative to Microsoft Office for creating unified project trackers, Gantt charts, and custom data summaries without pointer limitations.
- 1. Download and install WPS Office: Get WPS Office Free on your computer to access the Spreadsheet application.
- 2. Access project templates: Open WPS Spreadsheet and search for 'Project Management' or 'Gantt Chart' in the built-in Templates library.
- 3. Customize and consolidate: Customize the template with your own custom fields and track your consolidated project data seamlessly in a single unified file.

Frequently Asked Questions
Why does the ID field restart for each subproject in my MS Project master file?
The restarting ID fields indicate that the master project is dynamic and uses pointers to link to individual subproject files, rather than absorbing all the tasks into a single continuous database.
Is the summary line in the master project the exact same as the subproject summary task?
No, the summary line visible in the master project belongs exclusively to the master project. It acts as a container link and does not perfectly mirror all custom properties or fields from the subproject.
Can I force custom fields to sync between subprojects and the master project?
Not automatically through standard dynamic master links. You will either need to manually update the master project's summary line or use a custom VBA macro to programmatically pull and copy the custom field data.