Fix Incorrect Peak Units in a Microsoft Project Resource Report
Question details
The user needs to understand and correct Peak Units displayed as 500 rather than 5 in a monthly resource report.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A customized monthly resource report shows Peak Units while Max Units appears correct in the Resource Sheet.
- Observed behavior
- The report displays a Peak Units value of 500 where the user expects 5.
Open the affected report and note whether the value appears as 500, 500%, or 5. Compare it with the resource's Max Units in View > Resource Sheet; Peak Units and Max Units measure different things.
Check the report's Peak Units number format
Use this check to determine whether percentage formatting accounts for the difference between 500 and 5.
A value of 500% represents 5 units: percentage formatting displays an underlying value of 5 as 500%. Removing the percent sign alone does not necessarily convert the value.
Open the monthly resource report from the Report tab. Select the chart or table and confirm that it uses the Peak Units field.
If Peak Units is plotted on a chart, right-click the value axis and select Format Axis. Under Number, inspect the category and change it from Percentage to Number if that option is available and you want to display units rather than percentages.
Review the displayed values after the format change. If 500% becomes 5, the difference was percentage presentation; if it remains 500, inspect the report's source values and any custom calculations rather than assuming a formatting change will convert them.
Recreate the Resource Overview report
Use a fresh report to check whether customization is causing the unexpected display.
Review exported resource data with WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface. Use WPS Spreadsheets to review resource data exported to Excel format; it does not repair Microsoft Project reports or replace Project's scheduling features.

Frequently Asked Questions
Does 500% Peak Units mean five resources?
It represents five units of assignment capacity, but not necessarily five separate resources. Check the report's grouping and resource assignments to see what the value includes.
Why does Peak Units differ from Max Units?
Peak Units reflects the highest assignment level in a period, while Max Units represents a resource's maximum availability. Compare the report with View > Resource Sheet and the relevant assignments.
What if changing the chart axis format does not fix the value?
Check the chart's source field and any custom calculations, then compare it with a fresh Resource Overview report from the Report tab. A number format cannot correct an incorrectly calculated source value.
Where can I find my Microsoft Project version for support?
Open File > Account and select About Project. Include the version and update information when requesting further help.
Can WPS Office fix the report inside Microsoft Project?
No. WPS Spreadsheets can help you review data exported to an Excel file, but changes to the Project report must be made in Microsoft Project.