Question details
Resolve a calendar-name error when creating or applying a custom calendar in Microsoft Project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A user needs to apply a custom calendar to a project or make it available in linked project files.
- Observed behavior
- Microsoft Project displays an error indicating that the calendar name does not exist.
Open the affected project in Microsoft Project and note the exact calendar name shown in the error. If the project contains linked subprojects, identify their file locations so you can check each one.
Create and apply a custom calendar in Microsoft Project
Use this method when the custom calendar is missing or has not been applied to the project.
Open the affected project, then select Project > Change Working Time.
Select Create New Calendar, enter the desired name, and choose to create a copy of the Standard calendar. Adjust working times and exceptions as needed, then select OK.
Select Project > Project Information. In the Calendar list, choose the new calendar and select OK.
Open each linked subproject and use Project > Change Working Time to confirm that the required calendar is available. If it is missing, create it in that project and check its Project Information settings.

Test whether the calendar error affects new projects
Use a new project to help determine whether the error is limited to an existing file.
Manage project documents and spreadsheets with WPS Office
WPS Office is a free, lightweight alternative for everyday documents and spreadsheets, with a familiar interface and Microsoft Office format compatibility to make migration easier. Microsoft Project calendar errors must still be resolved in Microsoft Project.

Frequently Asked Questions
Where do I create a custom calendar in Microsoft Project?
Select Project > Change Working Time, then select Create New Calendar. Give it a name and choose to create a copy of the Standard calendar.
How do I apply the new calendar to my project?
Select Project > Project Information, choose the new calendar from the Calendar list, and select OK.
Why does a linked subproject report that the calendar does not exist?
The custom calendar may not be available in the subproject file. Open that file and check Project > Change Working Time; create the calendar there if it is missing.
What should I check if the error appears in a new project too?
Record the exact message and the step that triggers it, then check File > Account > About Project for your Microsoft Project version. Use those details when seeking further support.