How to Activate or Inactivate Tasks in Project Standard 2019

John WilsonJohn Wilson Oct 14, 2026 871 views

Question details

The user wants to know how to inactivate or exclude tasks in Microsoft Project Standard 2019 to report the percentage completion of only the active tasks.

How to Activate or Inactivate Tasks in Project Standard 2019
Product
Project Standard 2019
Device & OS
not provided
Scenario
Managing project schedules and attempting to exclude canceled or unnecessary tasks without permanently deleting them.
Observed behavior
The Inactivate Task command and Active field are missing in Project Standard 2019.
Before you start

Before applying workarounds, ensure you have administrative access to customize fields and views in your project file. It is also a good practice to save a copy of your current project schedule before altering task tracking structures.

Solution 1Recommended

Use Custom Fields and Filters to Hide Tasks

Since the native Inactivate feature is missing, setting up a custom Yes/No field allows you to manually tag and filter out canceled tasks.

This method replicates the visual exclusion of the missing feature. By filtering out tasks flagged as inactive, you can cleanly report the percentage completion of your actual active workflow without permanently deleting historical data.

1
Add a Custom Field

Right-click on a column header in your Gantt Chart view, select 'Custom Fields', choose 'Task' and select a 'Flag' field (e.g., Flag1). Rename it to 'Active Status'.

2
Mark tasks as inactive

Insert this new 'Active Status' column into your view. Change the value to 'No' for any tasks you want to cancel or exclude from your active tracking.

3
Create and apply a custom filter

Go to the View tab, click the Filter dropdown in the Data group, and select 'More Filters'. Create a new filter where 'Active Status' equals 'Yes'. Apply this filter to hide all inactive tasks from your current view.

Use Custom Fields and Filters to Hide Tasks
Reporting Accuracy: Once the filter is applied, you can accurately track and report on your active tasks without the canceled items cluttering your project summary.
Free Microsoft Office alternative

Enhance Your Productivity with WPS Office

While complex project scheduling might require specialized software, your daily documentation, spreadsheets, and presentations shouldn't be a hassle. WPS Office offers a free, lightweight, and comprehensive suite perfectly suited for managing project reports, budgets, and team communications.

  1. 1. Download the software: Visit the official WPS Office website and download the free installation package for your operating system.
  2. 2. Install and launch: Run the installer, follow the straightforward on-screen instructions, and open the application.
  3. 3. Open existing documents: Load your existing Microsoft Office files directly into WPS Office to continue working without any formatting loss.
Fully compatible with Microsoft Word, Excel, and PowerPoint formats (.docx, .xlsx, .pptx).Lightweight installation that runs smoothly even on older devices.Familiar tabbed user interface ensuring a seamless migration with zero learning curve.Built-in PDF tools for easily sharing secure project reports and documentation.
microsoft office alternative - wps office

Frequently Asked Questions

Why is the Inactivate Task button missing in my MS Project?

The Inactivate Task command and the Active field are premium features available only in Project Professional and Project Online Desktop Client. They are intentionally excluded from Microsoft Project Standard editions.

Does deleting a task affect the project baseline?

Yes, permanently deleting a task will remove its baseline data and affect your historical project tracking, including cost and resource allocations. This is why using a custom field to filter out tasks is recommended instead of deleting them.

How can I request Microsoft to add this feature to Project Standard?

You can suggest features or provide feedback by visiting the official Microsoft Feedback portal online and submitting a formal request for the Inactivate Task feature to be included in standard editions.

Can I track completion percentages if I simply hide inactive tasks?

Yes. By applying a custom filter to show only your active tasks, your views and custom reports can be tailored to reflect the progress and completion metrics of just the visible, active workload.