Why the Inactivate Task Button Is Missing in Project 2016
Question details
The user wants to know why the Inactivate Task command is missing in Microsoft Project 2016.
- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- The user wants to inactivate a task from the ribbon while working in Project 2016 Standard.
- Observed behavior
- The Inactivate Task command is unavailable in Project 2016 Standard and may appear to be missing from the ribbon.
Open Microsoft Project and check File > Account for the installed edition. The Inactivate Task feature is available in Project Professional, not Project 2016 Standard.
Use Project Professional to inactivate tasks
Use this solution if you need to remove a task from schedule calculations without deleting it.
In Project, select File > Account and look under Product Information for Standard or Professional.
If you have Standard, obtain and install a suitable licensed edition of Project Professional. Check with your administrator or Microsoft for available licensing options.
Open the project in Professional, select the task, and choose Task > Inactivate in the Schedule group.
Mark genuinely completed tasks as complete
Use this option in Project Standard to track work that has actually finished; it does not replace task inactivation.
Track project tasks in WPS Office
WPS Office is a free, lightweight alternative for everyday office work, with a familiar interface and Microsoft Office format compatibility to help you move between applications. Use WPS Spreadsheets for a separate task tracker; it does not add task inactivation to Microsoft Project.

Frequently Asked Questions
Can I add Inactivate Task to the ribbon in Project 2016 Standard?
No. Inactivate Task is a Professional feature, so ribbon customization cannot enable it in Project 2016 Standard.
How do I check which edition of Project 2016 I have?
In Project, select File > Account and check Product Information for the edition name.
Where is the Inactivate command in Project Professional?
Select a task, then look on the Task tab in the Schedule group for Inactivate.
Is marking a task complete the same as inactivating it?
No. A completed task remains part of the schedule, while an inactive task is excluded from schedule calculations. Use Task > 100% Complete only for work that is actually finished.