How to Concatenate Text and Duration Fields in Months in Microsoft Project
Question details
The user wants to format a Microsoft Project Duration field to display as months and concatenate it with a Text field.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Creating custom formulas to combine an existing text string with a duration value expressed in months instead of the default raw minutes.
- Observed behavior
- Because Microsoft Project stores duration internally in minutes, directly concatenating the Duration field outputs a large minute value instead of the expected month format.
Determine whether you need the output calculated in standard calendar months or strict working-time months, as this will change the formula you need to use.
Use the ProjDurConv Function for Standard Month Conversion
This method uses Microsoft Project's built-in conversion function to translate the raw duration minutes into standard month units before combining it with text.
The ProjDurConv function is the most reliable way to enforce a specific time unit in your formulas without manually calculating hours and days.
Right-click on any column header in your Gantt Chart view and select 'Custom Fields' from the context menu.
In the Custom Fields dialog box, ensure the 'Task' radio button is selected. Choose an available Text field (e.g., Text11) where you want the final concatenated result to appear.
Click on the 'Formula...' button located under the Custom attributes section to open the editor.
Type the formula: [Text10] & " + " & ProjDurConv([Duration], pjMonths). Replace 'Text10' with whichever field contains your initial text. Click 'OK' to save and apply.

Calculate Working Months Manually
If you need precise control over the definition of a working month (for example, strictly 20 working days per month), a manual mathematical conversion is necessary.
Try WPS Office for Your Everyday Document Needs
While Microsoft Project is built specifically for complex task scheduling, WPS Office is the perfect free alternative for all your standard word processing, spreadsheet, and presentation tasks, offering a lightweight experience and familiar interface.

Frequently Asked Questions
Why does the Microsoft Project Duration field show as minutes in my formula?
Internally, Microsoft Project stores all duration values in minutes, regardless of how they are formatted to display on your screen. When you reference a Duration field in a formula, the software retrieves this raw internal minute data unless a conversion function is applied.
How can I convert MS Project duration to working days in a custom formula?
You can use the formula [Duration]/[Minutes Per Day] to convert the raw minute data into standard working days based on your specific project calendar settings.
Can I format the concatenated text to include additional spaces or words?
Yes. In the formula editor, you can use the ampersand (&) operator alongside text wrapped in quotation marks to insert spaces, symbols, or custom words. For example, adding & " months " will append the word 'months' to the end of your string.