How to Create Monthly Recurring Tasks in Microsoft Project 2013

Camila MilosovichCamila Milosovich Nov 3, 2026 868 views

Question details

The user needs to set up a monthly planning schedule that contains recurring activities with multiple components occurring on different dates.

How to Create Monthly Recurring Tasks in Microsoft Project 2013
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
Creating a monthly schedule for repeating project activities such as reports, presentations, approvals, and status meetings.
Observed behavior
The goal is to correctly configure these recurring tasks without creating scheduling conflicts with task dependencies.
Before you start

Before adding tasks to your schedule, outline all repeating activities and their specific monthly dates to ensure accurate recurrence settings.

Solution 1Recommended

Create Separate Recurring Tasks Using the Task Ribbon

The recommended approach is to create individual recurring tasks for each repeating activity rather than linking them, which prevents scheduling conflicts.

Recurring tasks automatically receive a Start No Earlier Than (SNET) date constraint, pinning them to their scheduled dates. Mixing predecessors or successors with SNET constraints can cause scheduling problems, so it is best to avoid linking these tasks.

1
Select the Insertion Point

Click on the task row in your project schedule where you want to insert the new recurring activity.

2
Open the Recurring Task Dialog

Navigate to the Task tab on the top ribbon, click the drop-down arrow under Task, and select Recurring Task.

3
Enter Task Details

In the Recurring Task Information dialog box, type the name of the activity (e.g., Monthly Report) and specify its duration.

4
Set the Recurrence Pattern

Under Recurrence pattern, select Monthly. Choose the specific day the task occurs, such as the 5th of every month.

5
Define the Date Range

Set the range of recurrence by specifying the start and end dates. Leave the Calendar setting as 'None' unless a special working calendar is required, and click OK.

Create Separate Recurring Tasks Using the Task Ribbon
Handling Non-Working Days and Resources: If a scheduled day falls on a non-working day, Project will reschedule it to the next working day by default. Additionally, recurring tasks have a priority of 1000, ensuring that resource leveling will not delay them.
Free Microsoft Office alternative

Manage Project Schedules Easily with WPS Office

While Microsoft Project provides advanced scheduling tools, it can be complex and expensive. For many users and teams, project timelines, recurring tasks, and monthly schedules can be efficiently managed using WPS Spreadsheet. WPS Office is a free, lightweight suite that offers powerful spreadsheet capabilities with full Microsoft Excel compatibility.

  1. 1. Download and Install WPS Office: Visit the official WPS Office website to download and install the free suite on your device.
  2. 2. Open WPS Spreadsheet: Launch WPS Office and open a new Spreadsheet document to begin outlining your project tasks.
  3. 3. Use Built-in Templates: Click on 'Templates' in the application to search for project management, timeline, or Gantt chart templates to instantly organize your recurring tasks.
Completely free and lightweight alternative to Microsoft OfficeFully compatible with Microsoft Excel (.xlsx) formats for easy project trackingIncludes a rich library of free project management and Gantt chart templatesFamiliar user interface ensures a quick transition without a steep learning curve
microsoft office alternative - wps office

Frequently Asked Questions

Why shouldn't I link recurring tasks with predecessors and successors in MS Project?

Recurring tasks automatically use a Start No Earlier Than (SNET) constraint to lock them to their specific dates. Adding predecessors or successors conflicts with this hard constraint and can lead to scheduling errors and unpredictable task shifts.

What happens if a monthly recurring task falls on a weekend?

By default, Microsoft Project will attempt to reschedule the task to the next available working day. If the task must occur on that exact date regardless of weekends, you need to assign it a specific calendar where all days are marked as working days.

Will resource leveling delay my recurring tasks?

No. When you create recurring tasks in Microsoft Project, they are automatically assigned a priority of 1000. This high priority prevents the software's resource leveling engine from delaying them.