How to Customize Milestone Shapes and Colors in Microsoft Project
Question details
The user needs a way to assign different milestone symbols or colors to visually separate timeline items from different subprojects within a master project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Managing a complex master project containing multiple subprojects and attempting to distinguish between them visually on the timeline.
- Observed behavior
- Timeline milestone shapes and colors appear to be fixed, defaulting exclusively to diamond symbols and standard colors without options for individual customization.
Verify whether you are using Microsoft Project desktop or Project for the web, as timeline formatting capabilities differ between the two platforms.
Customize Gantt Bar Styles for Visual Differentiation
Since top-level timeline milestones are locked to standard shapes and colors, modifying Gantt bar styles is the best way to visually distinguish subprojects.
In Microsoft Project, timeline milestone shapes and colors are structurally fixed to use a standard diamond symbol. They cannot be assigned separate colors directly on the Timeline view. However, you can achieve the necessary visual differentiation for your subprojects by customizing the actual Gantt chart bars.
Navigate to the 'View' tab on the ribbon and select 'Gantt Chart' to display your project's detailed task bars.
Right-click anywhere in the blank space of the Gantt chart portion (the right side) and click 'Bar Styles' from the context menu.
In the Bar Styles dialog box, scroll to find the milestone or task style you want to alter, or create a new row for specific subproject tasks.
Use the 'Bars' tab at the bottom of the dialog to select distinct shapes, patterns, and colors that will uniquely identify the milestones or tasks of your different subprojects.
Modify Timeline Appearance in Project for the Web
If you are utilizing Project for the web (Project Web App), you can apply limited appearance modifications directly to the timeline.
Manage Project Timelines Easily with WPS Office
If you find Microsoft Project's rigid formatting limitations frustrating or the licensing too expensive, WPS Office is an excellent alternative. Using WPS Spreadsheet, you can create highly customizable project timelines and Gantt charts with complete freedom over milestone shapes and colors.
- 1. Download WPS Office: Install WPS Office for free from the official website.
- 2. Open a Timeline Template: Launch WPS Spreadsheet, go to the template library, and search for 'Gantt Chart' or 'Project Timeline'.
- 3. Customize Your Milestones: Use built-in shape and color tools to visually distinguish all of your subprojects without restriction.

Frequently Asked Questions
Can I change the default diamond milestone shape in Microsoft Project?
No. In the standard Timeline view of Microsoft Project, milestone shapes are fixed as diamond symbols and cannot be customized.
How do I change the color of a single task bar in MS Project?
Double-click the specific task bar directly in the Gantt Chart view to open the Format Bar dialog box. From there, you can adjust the shape, pattern, and color for just that individual task.
Is there a way to color-code subprojects entirely?
Yes, you can visually color-code subprojects in the Gantt Chart view by using the Bar Styles menu to set conditional formatting based on specific Flags or custom fields assigned to each subproject.