How to Fix One-Minute Scheduling Errors in Microsoft Project
Question details
The user needs to resolve an issue in Microsoft Project where tasks finish one minute late (e.g., 5:01 PM instead of 5:00 PM), causing subsequent auto-scheduled tasks to shift by one minute.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Creating and managing auto-scheduled project tasks using custom calendar shifts.
- Observed behavior
- Tasks are finishing at irregular times like 5:01 PM instead of rounding to the exact hour, causing cascading one-minute delays for all later linked tasks.
Change your project's date format to include time values (e.g., '1/28/23 12:33 PM') so you can accurately observe exactly when tasks start and finish down to the minute.
Verify and Align Project Start Time with Custom Calendars
Ensure that the start time in your Project Information matches the shift start times of your custom working calendar to prevent minute-level offsets.
One-minute scheduling errors usually occur when the project's overall start time differs slightly from the working shift times defined in your calendar. Aligning these times resolves cascading delays.
Navigate to File > Options > General. Under the 'Project view' section, change the 'Date format' to a setting that includes both the date and the time.
Go to Project > Change Working Time. Instead of modifying the Standard calendar directly, click 'Create New Calendar' to make a copy. Set up your custom 12-hour shifts and weekend schedules here.
Navigate to Project > Project Information. Review the Start Date and time.
Adjust the project start time so it perfectly aligns with the exact beginning of the shift in your newly created custom calendar.

Review Task Dependencies, Constraints, and Resource Calendars
Check for conflicting working times between project, task, and resource calendars that might introduce a time offset.
Manage Project Schedules with WPS Spreadsheet
If you are dealing with complex Microsoft Project scheduling errors, consider simplifying your workflow. WPS Office provides a free, lightweight spreadsheet tool perfectly suited for project tracking, task scheduling, and Gantt charts without the hassle of minute-level calendar conflicts.
- 1. Download and Install: Get WPS Office Free from the official website and install it on your device.
- 2. Open a Project Template: Launch WPS Spreadsheet, go to the homepage, and search for 'Project Schedule' or 'Gantt Chart' templates.
- 3. Customize Your Timeline: Easily input your tasks, durations, and start dates without worrying about hidden calendar conflicts.

Frequently Asked Questions
Why do my Microsoft Project tasks start at odd times like 8:01 AM?
This usually happens when the overall Project Start Date time does not exactly match the shift start time defined in your working calendar, or when a predecessor task forces a one-minute offset due to mismatched resource calendars.
Should I edit the Standard calendar directly in Microsoft Project?
No, it is highly recommended to create a copy of the Standard calendar and apply your customizations (like 12-hour shifts or weekend work) to the copy. This prevents altering default project settings globally.
How can I see the exact time a task finishes in Microsoft Project?
Go to File > Options > General. Under the 'Project view' section, change the 'Date format' dropdown to a format that explicitly includes the time of day alongside the date.