How to Import Tasks from a Shared Outlook Inbox into MS Project

Maira MehtabMaira Mehtab Nov 4, 2026 870 views

Question details

The user needs to import tasks from a shared team Outlook inbox directly into Microsoft Project.

How to Import Tasks from a Shared Outlook Inbox into Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Managing team tasks by transferring them from a shared Outlook mailbox into MS Project without having to manually re-assign every task.
Observed behavior
Microsoft Project lacks a direct import feature for shared team inboxes, forcing users to use tedious workarounds like assigning every task to themselves first.
Before you start

Verify whether your shared Outlook inbox is connected to a Microsoft 365 group and has an associated Planner plan, as this determines the method for exporting your tasks.

Solution 1Recommended

Export Shared Mailbox Tasks via Microsoft Planner and Excel

Use this method if your shared mailbox is part of a Microsoft 365 group linked to Planner. By exporting to Excel first, you can easily pull the data into MS Project.

Microsoft Project cannot directly pull tasks from shared inboxes. However, if your shared inbox is configured as a Microsoft 365 group, those tasks are usually managed in Microsoft Planner. You can bridge the gap by exporting the Planner tasks to an Excel workbook and then importing that workbook into Project.

1
Locate the Connected Planner Plan

In Outlook, hover your cursor over the Microsoft 365 group associated with your shared inbox. If it is a group, click on 'Planner' in the popup card to open the connected plan in your web browser.

2
Export Tasks to Excel

Inside Microsoft Planner, click the '...' (More options) menu at the top of the plan interface and select 'Export plan to Excel' to download your task list as an .xlsx file.

3
Import Excel into Project

Open Microsoft Project, navigate to 'File' > 'Open', select your downloaded Excel workbook, and follow the Import Wizard prompts to map the Excel columns to your Project schedule fields.

Export Shared Mailbox Tasks via Microsoft Planner and Excel
Account Permissions: You must have the necessary member permissions within the Microsoft 365 group to access the Planner plan and export the data.
Free Microsoft Office alternative

Manage Your Exported Task Data Easily with WPS Office

While Microsoft Project manages your complex timelines, you can smoothly handle exported task lists, team reports, and spreadsheet data using WPS Office. It provides a highly compatible, lightweight, and free alternative to Microsoft Office for your everyday document needs.

  1. 1. Download and Install WPS Office: Download the free WPS Office suite from the official website and follow the installation wizard.
  2. 2. Open Exported Data: Launch WPS Spreadsheets and open the .xlsx file you exported from Microsoft Planner.
  3. 3. Edit and Prepare Your Data: Clean up your task list, adjust the columns for easier mapping, save the file, and proceed to import it into your project management software.
Fully compatible with Microsoft Excel (.xlsx), Word, and PowerPoint formats.Easily view, edit, and format exported Planner task lists before importing them into Project.Lightweight installation and familiar user interface for a seamless transition.Free to use with powerful built-in PDF editing and data analysis tools.
microsoft office alternative - wps office

Frequently Asked Questions

Can I directly link a shared Outlook inbox to MS Project?

No, Microsoft Project does not currently support directly linking or importing tasks straight from a shared team mailbox. You must use an intermediary step, such as exporting via Microsoft Planner to Excel, or assigning the tasks to your personal account first.

How do I know if my shared inbox is a Microsoft 365 group?

In Outlook, hover your cursor over the shared inbox name in your folder pane. If it is a Microsoft 365 Group, a detailed contact card will appear showing group details and offering links to group resources like Planner, Files, and SharePoint.

Why are my exported Excel tasks not importing correctly into Project?

This usually occurs if the columns in your exported Excel file are not mapped properly to MS Project's fields. During the Import Wizard in Microsoft Project, make sure that columns such as 'Task Name', 'Start Date', and 'Due Date' are mapped accurately to the corresponding Project fields.