How to Limit a Microsoft Project Resource to 10 Hours per Week
Question details
The user needs to restrict a resource's availability to a maximum of 10 hours per week in Microsoft Project to prevent them from being overallocated.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Managing team resource scheduling and individual capacities within a project plan.
- Observed behavior
- Default resource calendars and maximum units do not automatically prevent overallocation without configuring specific 10-hour weekly constraints or capacity settings.
Ensure you have access to the Resource Sheet view in your Microsoft Project file and understand whether the team member works fixed daily hours or a flexible schedule before modifying their capacity.
Create a Custom Resource Calendar for Fixed Hours
Set up a dedicated calendar that only allows the resource to work exactly 10 specific hours per week (e.g., 2 hours per day). Use this if the resource's schedule is rigid.
This method is ideal for part-time resources who work a strict, predictable schedule. By defining exact working times, Microsoft Project will only schedule their tasks during these designated hours.
Navigate to the 'Project' tab on the ribbon and click on 'Change Working Time'.
Click 'Create New Calendar', name it (e.g., '10-Hour Part-Time'), select 'Make a copy of Standard', and click 'OK'.
Go to the 'Work Weeks' tab, click 'Details', select Monday through Friday, and adjust the working times to reflect only 2 hours per day (e.g., 08:00 AM to 10:00 AM).
Open the 'Resource Sheet' view, double-click the target resource to open 'Resource Information'. Under the 'General' tab, change the 'Base calendar' to your newly created 10-hour calendar.

Use Maximum Units for Flexible 10-Hour Capacity
If the 10 hours can be distributed flexibly across the week, adjust the resource's Maximum Units to 25% of a standard 40-hour work week.
Try WPS Office for Your General Document and Project Tracking Needs
While Microsoft Project handles complex automated scheduling, WPS Office provides a free, lightweight, and easy-to-use alternative for general project management and team collaboration. You can easily build Gantt charts, resource tracking sheets, and project reports using WPS Spreadsheet.
- 1. Download WPS Office: Visit the official WPS Office website and download the free installation package for your device.
- 2. Open a Project Template: Launch WPS Spreadsheet, go to the template library, and search for 'Project Management' or 'Gantt Chart'.
- 3. Track Resource Hours: Use the built-in formulas and scheduling templates to easily monitor your team's weekly resource hours without complex configurations.

Frequently Asked Questions
Why is my resource still showing as overallocated after changing their max units to 25%?
Changing the Maximum Units only limits their recognized capacity. If they are already assigned to tasks requiring more than 10 hours of work in a given week, they will instantly show as overallocated. You must run Resource Leveling or manually reduce their assigned work hours for those tasks.
Should I use a custom calendar or adjust Maximum Units for part-time resources?
Use a custom calendar if the resource works specific, fixed hours (e.g., exactly 8 AM to 10 AM daily). Use Maximum Units (like 25%) if they work 10 hours flexibly throughout the standard work week and their exact daily hours don't matter.
Does Resource Leveling automatically fix all overallocations in Microsoft Project?
No. Microsoft Project's resource leveling can delay tasks to resolve schedule overlaps, but it may not resolve all overallocations if project constraints, deadlines, or task dependencies prevent tasks from moving. Manual review in the Resource Usage view is often necessary.