How to Remove Completed Project Online Tasks from Timesheets

Steve KSteve K Oct 1, 2026 868 views

Question details

Users need to remove finished tasks from team timesheets without deleting historical work and assignment data.

How to Remove Completed Project Online Tasks from Timesheets
Product
Project Online
Device & OS
not provided
Scenario
Managing active team timesheets and closing out completed tasks to prevent timesheet clutter.
Observed behavior
Tasks that are considered completed continue to appear on team timesheets because they have not been correctly finalized and published.
Before you start

Ensure you have the necessary Project Manager permissions to update task progress and publish project changes to the server.

Solution 1Recommended

Mark Tasks as 100% Complete and Publish

The correct method to hide tasks from active timesheets while keeping the project history intact.

A common mistake is removing users from a task to stop it from appearing on their timesheet. This deletes the historical record of their work. Instead, marking the task as fully complete ensures the historical assignment data is preserved while simultaneously hiding the task from future active timesheets.

1
Open your project

Navigate to Project Online and open the specific project containing the lingering tasks in the Project Web App or the Project Desktop client.

2
Locate unfinished tasks

Find the tasks that team members have finished but are still appearing on their active timesheets.

3
Set completion to 100%

Update the '% Complete' field for these specific tasks to exactly 100%.

4
Publish the project

Save your changes and click the 'Publish' button. The server must process this update before the tasks are successfully removed from team members' timesheets.

Mark Tasks as 100% Complete and Publish
Preserve Assignment History: Do not remove the assigned users from the task line. Completing the task maintains their historical assignment and work information for reporting.
Free Microsoft Office alternative

Manage Your Project Data Efficiently with WPS Office

While managing Project Online timesheets requires Microsoft tools, you can seamlessly track project budgets, timelines, and reporting using WPS Office. It is a powerful, lightweight, and free alternative to Microsoft Office that supports all your data management needs.

  1. 1. Download and Install: Get WPS Office from the official website and install it on your computer or mobile device.
  2. 2. Open Project Files: Open any exported Microsoft Excel project logs or timesheets directly in WPS Spreadsheet.
  3. 3. Edit and Collaborate: Use the familiar interface to edit task progress, generate project reports, and save in universally compatible formats.
Free, lightweight, and incredibly easy to useHigh compatibility with Microsoft Excel (.xlsx), Word (.docx), and PowerPoint (.pptx) formatsFamiliar user interface for seamless migration and minimal learning curveCreate custom project tracking templates and custom team timesheets
microsoft office alternative - wps office

Frequently Asked Questions

Why do fully completed tasks still show up on timesheets after updating?

If tasks still appear after being marked 100% complete, it is usually because the project manager has not published the changes. You must click 'Publish' after updating the task status so the server can push the updates to the team timesheets.

Can I just delete the task assignment to remove it from the timesheet?

It is highly recommended not to delete the user assignment. Doing so will permanently delete the historical record of the work performed by that user. Marking the task as 100% complete is the proper way to remove it from view while preserving the data.

Does marking a summary task as 100% complete affect its subtasks?

Yes, updating a summary task to 100% complete will automatically mark all of its underlying subtasks as 100% complete as well. Once published, all of these subtasks will be removed from active timesheets.