How to Use a Separate Overtime Rate for Microsoft Project Tasks
Question details
The user needs to assign different hourly rates to a Microsoft Project resource for specific tasks without changing task duration or adding unwanted regular hours when overtime hours are entered.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A resource performs different types of work at different hourly rates, and overtime hours should not increase normal hours for those tasks.
- Observed behavior
- Microsoft Project adds normal hours when overtime hours are entered, and the resource currently uses one standard rate for all tasks.
Open the relevant project in Microsoft Project and identify the resource and tasks that require the separate overtime or task-specific rate. Confirm that you can switch between Resource Sheet view and Resource Usage view.
Create an alternate cost rate table and apply it to specific tasks
Use this method when one resource needs different hourly rates for different tasks without changing task duration or adding unwanted regular hours.
Microsoft Project stores up to five cost rate tables for each resource, labeled A through E. Creating a second table keeps the original rate intact and allows you to assign the alternate rate only to selected task assignments.
In Microsoft Project, go to the View tab or Resource views and select Resource Sheet.
Double-click the relevant resource to open the Resource Information dialog, then select the Costs tab.
Click the Cost Rate Table B tab, enter the standard rate, overtime rate, or per-use cost needed for the separate tasks, and confirm with OK.
Go to the View tab or Resource views and select Resource Usage to see resource-task assignments.
Add the Cost Rate Table column to the Resource Usage view, then select B in that column for each task assignment that should use the alternate rate.

Use WPS Office as a Free Microsoft Office Alternative for Project Data
WPS Office is a free, lightweight Microsoft Office alternative that handles spreadsheets, documents, and presentations with familiar tools. When you export Microsoft Project data to Excel or CSV, WPS Office makes it easy to view, edit, and share task, resource, and cost information without a subscription.

Frequently Asked Questions
Can I assign different pay rates to the same resource for different tasks in Microsoft Project?
Yes. Create an alternate cost rate table in the resource's Costs tab, then add the Cost Rate Table column in Resource Usage view and select that table for the tasks that need the different rate.
How do I stop Microsoft Project from adding normal hours when I enter overtime hours?
Use a separate cost rate table for the assignment and enter overtime hours in the Overtime Work field. Adding overtime work does not change the task duration or add regular hours when the assignment is configured correctly.
Does changing the Cost Rate Table affect task duration?
No. The cost rate table only changes cost calculations. It does not change task duration, scheduled work, or resource availability.
Can WPS Office open Microsoft Project .mpp files?
WPS Office does not open native .mpp files. However, you can export Microsoft Project data to Excel or CSV and open, edit, or analyze that data in WPS Office.