How to Use Hammock Tasks to Link Dates in Microsoft Project
Question details
The user needs to create a generic task that dynamically adopts the start date of a Start Milestone and the end date of an End Milestone, updating automatically without other dependencies.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Creating dynamic date links between specific milestones because standard summary task dependencies are not permitted.
- Observed behavior
- Microsoft Project restricts tasks from depending directly on their own summary tasks. To link dates dynamically, users must use a hammock-task configuration or linked milestones.
Ensure your Microsoft Project schedule is properly outlined and that your Start and End milestones are clearly defined before establishing dynamic link relationships.
Create a Hammock Task Using Paste Special
Use the Paste Link feature to tie a generic task's start and finish dates directly to your milestone tasks.
A hammock task spans the duration between two specific dates, such as a Start and End milestone. Because Microsoft Project restricts tasks from depending on their own summary tasks to prevent circular logic, copying and pasting dates as links provides a practical workaround.
Add a Start Milestone at the top of your project phase and an End Milestone at the bottom.
Select the Start date cell of the Start Milestone, right-click it, and choose Copy.
Select the Start date cell of your generic hammock task. Go to the Task tab, click the drop-down arrow under Paste, select Paste Special, choose Paste Link, and click OK.
Copy the Finish date from the End Milestone. Select the Finish date cell of your generic hammock task, open the Paste Special dialog again, select Paste Link, and click OK.

Use Standard Predecessor and Successor Linking
If you want to avoid potential maintenance issues with Paste Links, use standard dependency links to group tasks logically between milestones.
Manage Project Documentation Easily with WPS Office
While Microsoft Project is strictly for complex project scheduling, WPS Office is the perfect lightweight companion for drafting your project reports, financial spreadsheets, and presentation decks. It provides robust capabilities for your daily documentation needs.

Frequently Asked Questions
What exactly is a hammock task in Microsoft Project?
A hammock task is a task whose duration is driven by the start date of one task (usually a Start Milestone) and the finish date of another task (an End Milestone). It automatically expands or shrinks as the associated milestone dates change.
Why does Microsoft Project prevent linking a task to its own summary task?
Project prevents tasks from linking to their own summary tasks to avoid circular reference errors. If allowed, a change in a subtask would change the summary task, which would in turn attempt to change the subtask infinitely.
Why do Paste Links sometimes break in project files?
Paste Links use Object Linking and Embedding (OLE) technology to share data between cells. If tasks are frequently deleted, moved, or if the project file itself is renamed or moved to a different directory, the background pathways can become corrupted or orphaned.