Question details

Plan shared resources across module tasks while tracking delivery dates, costs, and decisions about subsequent modules.

Manage Shared Resources Across Microsoft Project Tasks
Product
Microsoft Project
Device & OS
not provided
Scenario
Resources must be shared among validation, testing, training, and documentation activities for multiple modules.
Observed behavior
Microsoft Project may not automatically move resources into gaps between tasks and then return them to earlier work as desired.
Before you start

Identify the module delivery dates, dependencies, available resource capacity, and level of task detail you need to track. Confirm whether resources can actually work on multiple activities at the same time before changing their capacity.

Solution 1Recommended

Model Parallel Tasks and Level Shared Resources

Use this approach when module delivery dates and costs matter more than modeling every resource switch.

Resource leveling can delay or split work to address overallocations, but it does not guarantee that resources will fill every gap and return to earlier tasks in the desired order.

1
Set task durations

In the Gantt Chart, open each module activity's Task Information dialog, select the Advanced tab, and set Task type to Fixed Duration where appropriate.

2
Arrange parallel activities

In the Gantt Chart, review predecessors and remove unnecessary dependencies so activities can run in parallel when the work allows it. Keep genuine dependencies and module decision points.

3
Assign shared resources

Select a task and use Resource > Assign Resources to assign the people or resources needed for validation, testing, training, and documentation.

4
Review resource capacity

Open View > Resource Sheet and check Max. Units for each shared resource. Increase the value only if additional capacity is genuinely available.

5
Level and review

Open Resource > Leveling Options, consider a coarser Look for overallocations setting such as Week by Week, and select Level All. Review the resulting dates and assignments in the Gantt Chart and Resource Usage views.

Model Parallel Tasks and Level Shared Resources
Check the leveling result: A coarser overallocations setting may overlook conflicts within shorter periods. Verify that the schedule remains workable and that module delivery and decision dates are acceptable.
Free Microsoft Office alternative

Track Module Work and Costs in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for working with compatible Microsoft Office files. Use WPS Spreadsheets to maintain a simple manual resource and cost tracker, but continue using Microsoft Project for its scheduling and resource-leveling features.

Track module assignments, dates, and costs in a spreadsheetOpen and edit compatible Microsoft Excel XLSX filesUse a familiar interface for a smoother move from Office spreadsheetsWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Can Microsoft Project automatically fill every resource gap?

Not necessarily. Resource leveling addresses overallocations, but it may not place work into every gap or return a resource to an earlier task in the order you intend. Use View > Resource Usage to inspect and adjust detailed assignments.

When should I increase a resource's Max. Units?

Increase Max. Units in View > Resource Sheet only when additional capacity is genuinely available, such as when the resource represents a larger team. Raising the value without real capacity can hide overallocations.

What does Fixed Duration do for a module task?

A fixed-duration task keeps its duration fixed when certain assignment values change. Set it in Task Information > Advanced; it does not by itself ensure that resources are available or that tasks run in parallel.