Prevent Microsoft Project Resource Leveling from Hanging on Weekend Tasks

Olivia MillerOlivia Miller Nov 14, 2026 868 views

Question details

Prevent resource leveling from hanging when Microsoft Project contains specially scheduled weekend tasks.

Prevent Microsoft Project Resource Leveling from Hanging on Weekend Tasks
Product
Microsoft Project
Device & OS
not provided
Scenario
Tasks use a special weekend calendar, ignore resource calendars, and are scheduled outside normal Monday-to-Friday working hours.
Observed behavior
The tasks schedule correctly before leveling, but resource leveling hangs or crashes.
Before you start

Identify the weekend tasks that use the special task calendar and ignore resource calendars. Check that they are scheduled as intended before running resource leveling.

Solution 1Recommended

Set weekend task priority to 1000 before leveling

Use this workaround to keep specially scheduled weekend tasks out of resource leveling while allowing Project to level eligible tasks.

1
Show the Priority column

Open the project in Gantt Chart view, right-click a column heading, and select Insert Column. Choose Priority.

2
Set weekend task priorities

For each affected weekend task, enter 1000 in its Priority field. This tells Project not to level that task.

3
Run resource leveling

On the Resource tab, select Level All to level the eligible tasks. Check that the weekend tasks retain their intended positions.

4
Review resource conflicts

Open the Resource Usage view from the View tab and review any remaining resource overallocation. Adjust eligible tasks or assignments if conflicts remain.

Set weekend task priority to 1000 before leveling
Weekend tasks will not be leveled: A priority of 1000 prevents Project from moving those tasks to resolve resource conflicts. Overallocation can remain if other tasks cannot be adjusted sufficiently.
Free Microsoft Office alternative

Track project task lists in WPS Office

WPS Office is a free, lightweight alternative for managing project task lists and other office documents. Its familiar interface and Microsoft Office format compatibility make it easy to move existing spreadsheets and documents into your workflow. It does not fix Microsoft Project resource leveling.

Track weekend tasks and resource assignments in a spreadsheetOpen and edit Microsoft Excel XLSX and Word DOCX filesWork with a familiar, easy-to-use office interfaceUse a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why set a weekend task's priority to 1000?

In Microsoft Project, priority 1000 prevents resource leveling from moving the task. This can avoid the leveling conflict affecting specially scheduled weekend work.

How do I find the Priority field in Microsoft Project?

In Gantt Chart view, right-click a column heading, select Insert Column, and choose Priority. Enter the desired value for each affected task.

Will priority 1000 resolve resource overallocation?

Not necessarily. Project can level other eligible tasks, but the protected weekend tasks will not move. Check the Resource Usage view for remaining overallocation.

Can WPS Office fix Microsoft Project resource leveling?

No. WPS Office can help track tasks and assignments in an Excel-compatible spreadsheet, but it does not fix Microsoft Project's resource-leveling behavior.