Microsoft Project Online: Why You Cannot Link Tasks to Planner
Question details
Project Plan 3 and Microsoft 365 users want to know why they cannot find an option to link Project Online tasks to Microsoft Planner and whether configuration is required.

- Product
- Microsoft Project Online, Microsoft Project desktop client, and Microsoft Planner
- Device & OS
- not provided
- Scenario
- Connect a Microsoft Project task to an existing Planner plan.
- Observed behavior
- The Planner linking option is not available in Project Online. The reported feature appears to be supported in the Project desktop client, and it links to a plan rather than transferring tasks.
Check whether you are using Project Online in a browser or the Project desktop client. Have the target Planner plan ready and confirm that your work or school account can open it.
Check for Planner linking in the Project desktop client
Use this approach to connect a Project task to an existing Planner plan when the linking feature is available in your desktop client.
The reported linking feature belongs to the Project desktop client, not the Project Online browser interface. A missing button in Project Online therefore does not, by itself, indicate a configuration problem.
The link connects a Project task to a Planner plan. It does not create Planner tasks or copy the Project task into that plan.
Launch Microsoft Project desktop and open the project containing the task you want to link. Do not look for this feature in the Project Online browser interface.
In the task list, select the task that should serve as the connection to your Planner plan.
Open the Task tab and look for the Planner button. If it is available, select it to open the plan-linking pane. If it is missing, have your Microsoft 365 administrator verify feature availability for your desktop version and account.
In the linking pane, locate the group and Planner plan you can access, then use the available link command to connect the selected Project task to that plan.

Create Planner tasks manually when you need task transfer
Use this approach if your actual goal is to put Project work into Planner rather than link to a plan.
Use WPS Office for Supporting Project Documents and Task Lists
WPS Office is a free, lightweight, easy-to-use alternative for the documents and spreadsheets that support your project work. Its familiar interface and Microsoft Office format compatibility make migration straightforward. It does not fix Project Online–Planner linking or replace Microsoft Project scheduling.

Frequently Asked Questions
Do I need to enable a setting in Project Online to see the Planner link option?
The reported feature is available in the Project desktop client rather than the Project Online browser interface. Open the project in the desktop client and check the Task tab for the Planner button instead of looking for a Project Online setting.
Will linking a Project task create tasks in Microsoft Planner?
No. The feature links the selected Project task to an existing Planner plan. It does not create Planner tasks, transfer the Project task, or synchronize task details.
Can I link to an empty Planner plan?
Yes. The target plan can be empty or already contain tasks. Linking to an empty plan does not fill it with Project tasks; open Planner and use Add task to create them.
Why is the Planner button missing in my Project desktop client?
The QA record does not establish every version or account requirement. Check the Task tab in the desktop client, then ask your Microsoft 365 administrator to verify whether the linking feature is available for your installed version and account. A Project Plan 3 subscription alone does not confirm that the button will appear in every interface.
Can WPS Office fix this Project Online integration issue?
No. WPS Office does not enable Project Online–Planner linking. You can use WPS Spreadsheet for a separate task tracker and WPS Writer or Presentation for supporting project documents, including compatible Microsoft Office files.




