Record Actual Work Without Changing Duration in Microsoft Project
Question details
The user needs to record person-days spent on a task separately from its duration without assigning a resource.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A high-level project plan uses task dependencies and sequencing but does not require detailed resource tracking.
- Observed behavior
- Entering actual work can cause Microsoft Project to recalculate task scheduling values, including duration.
Check the task's current duration and dependencies in the Gantt Chart view. Decide whether the recorded person-days must appear in Project's built-in Actual Work field or can be kept in a separate custom field.
Record Person-Days in a Custom Field Without Assigning Resources
Use a custom field when you need to track effort independently of Project's scheduling calculations.
A custom field stores your entry without making it Project's built-in Actual Work value. The task can retain its dependencies and scheduled duration while the separate field records person-days.
Go to View > Gantt Chart and locate the task whose effort you want to record.
Right-click a column heading, select Insert Column, and choose Number1. Use Text1 instead if you prefer to enter a value with a label, such as “5 person-days.”
Click the new field for the task and enter the person-days spent. For Number1, enter a number such as 5 and use the field consistently for person-days.
Review the Duration, Start, and Finish columns in the Gantt Chart grid to confirm the task still reflects the intended schedule.

Use a Fixed-Duration Task and Review Actual Work
Use this approach when you need Project's built-in work tracking and are prepared to review scheduling changes.
Track Person-Days in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for working with Office documents. Use WPS Spreadsheets to maintain a separate person-day log alongside your Project plan; it does not fix Microsoft Project scheduling or replace its dependency engine.

Frequently Asked Questions
Can I record person-days without assigning a resource?
Yes. In View > Gantt Chart, insert a custom field such as Number1 and enter the person-days there. This does not populate Project's built-in Actual Work field.
Why can entering actual work change a task's duration?
Project uses the relationship between work, duration, and assignment units when scheduling tasks. The result also depends on task type, assignments, calendars, and the values you change.
Does Fixed Duration prevent all schedule changes?
No. Set it under Task Information > Advanced to keep duration fixed for certain work and unit changes, but actual dates, constraints, calendars, and other updates can still affect the schedule.
Will a custom person-days field appear in Actual Work reports?
No. Number1 and Text1 are separate from the built-in Actual Work field. Include the custom field in a view or report if you want to display those entries.