The user needs to record person-days spent on a task separately from its duration without assigning a resource.

Record Actual Work Without Changing Duration in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A high-level project plan uses task dependencies and sequencing but does not require detailed resource tracking.
Observed behavior
Entering actual work can cause Microsoft Project to recalculate task scheduling values, including duration.
Before you start

Check the task's current duration and dependencies in the Gantt Chart view. Decide whether the recorded person-days must appear in Project's built-in Actual Work field or can be kept in a separate custom field.

Solution 1Recommended

Record Person-Days in a Custom Field Without Assigning Resources

Use a custom field when you need to track effort independently of Project's scheduling calculations.

A custom field stores your entry without making it Project's built-in Actual Work value. The task can retain its dependencies and scheduled duration while the separate field records person-days.

1
Open the task grid

Go to View > Gantt Chart and locate the task whose effort you want to record.

2
Add a custom field

Right-click a column heading, select Insert Column, and choose Number1. Use Text1 instead if you prefer to enter a value with a label, such as “5 person-days.”

3
Record the effort

Click the new field for the task and enter the person-days spent. For Number1, enter a number such as 5 and use the field consistently for person-days.

4
Check the schedule

Review the Duration, Start, and Finish columns in the Gantt Chart grid to confirm the task still reflects the intended schedule.

Record Person-Days in a Custom Field Without Assigning Resources
Custom values are not Actual Work: A Number1 or Text1 entry will not update Project's Actual Work totals, resource usage, or work-based reports.
Free Microsoft Office alternative

Track Person-Days in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for working with Office documents. Use WPS Spreadsheets to maintain a separate person-day log alongside your Project plan; it does not fix Microsoft Project scheduling or replace its dependency engine.

Record task durations and person-days in separate spreadsheet columnsOpen and save Microsoft Excel XLSX files for sharingUse a familiar spreadsheet interface to maintain a simple effort logWork with a free, lightweight Office alternative
microsoft office alternative - wps office

Frequently Asked Questions

Can I record person-days without assigning a resource?

Yes. In View > Gantt Chart, insert a custom field such as Number1 and enter the person-days there. This does not populate Project's built-in Actual Work field.

Why can entering actual work change a task's duration?

Project uses the relationship between work, duration, and assignment units when scheduling tasks. The result also depends on task type, assignments, calendars, and the values you change.

Does Fixed Duration prevent all schedule changes?

No. Set it under Task Information > Advanced to keep duration fixed for certain work and unit changes, but actual dates, constraints, calendars, and other updates can still affect the schedule.

Will a custom person-days field appear in Actual Work reports?

No. Number1 and Text1 are separate from the built-in Actual Work field. Include the custom field in a view or report if you want to display those entries.