Fix Insufficient Permissions for Resource Scheduling in Project for the Web

Ayan MasoodAyan Masood Oct 29, 2026 868 views

Question details

Users are encountering a specific permission error when attempting to connect the Resource Scheduling app to Project for the web.

Fix Insufficient Permissions for Resource Scheduling in Project for the Web
Product
Power Apps / Project for the web
Device & OS
not provided
Scenario
Connecting the Resource Scheduling Power App to Project for the web to manage project resources.
Observed behavior
The system throws a permission error for 'prvCreateMsdyn_resourcerequirementdetail', preventing the successful connection and usage of the scheduling tool.
Before you start

You must have Microsoft Dynamics 365 or Power Apps administrator privileges to modify security roles and grant the required entity permissions.

Solution 1Recommended

Grant Entity Permissions via Power Apps Admin Center

Update the security roles in the Power Apps admin center to include the Resource Requirement Detail custom entity.

This error occurs because the user's assigned role lacks the necessary 'Create' privileges for the resource requirement detail entity. An administrator must explicitly grant this access.

1
Access Power Apps Admin Center

Log into the Microsoft Power Platform admin center using an administrator account.

2
Select the Environment

Navigate to the 'Environments' tab and select the specific environment where the Resource Scheduling app is hosted.

3
Modify Security Roles

Go to 'Settings', expand 'Users + permissions', click on 'Security roles', and locate the role currently assigned to the affected user.

4
Grant Entity Permissions

Search for the 'Resource Requirement Detail' custom entity and grant the required create permissions (prvCreateMsdyn_resourcerequirementdetail) to the role.

5
Retest the Connection

Instruct the user to sign out of the Power App, sign back in, and test the connection to Project for the web to confirm the issue is resolved.

Grant Entity Permissions via Power Apps Admin Center
Changes applied successfully: Security role updates may take a few moments to propagate. Re-logging ensures the newest permission token is fetched.
Free Microsoft Office alternative

Boost Your Daily Productivity with WPS Office

While complex resource scheduling requires specialized platforms like Power Apps and MS Project, your daily documentation doesn't need to be complicated. WPS Office provides a free, lightweight, and highly compatible suite for your documents, spreadsheets, and presentations.

  1. 1. Download the Installer: Visit the official WPS Office website and download the free installation package for your operating system.
  2. 2. Install the Suite: Run the installer and follow the quick on-screen instructions to set up the software.
  3. 3. Open Office Files: Launch WPS Office and instantly open your existing Microsoft Office files without any format shifting.
Free and lightweight office suite with no complex permission configurations required.Fully compatible with Microsoft Word, Excel, and PowerPoint file formats.Familiar user interface ensuring a zero-learning-curve transition for new users.Built-in PDF toolkit to edit, merge, and convert project reports seamlessly.
microsoft office alternative - wps office

Frequently Asked Questions

What does the prvCreateMsdyn_resourcerequirementdetail error mean?

It indicates that the user's assigned security role in Power Apps lacks the 'Create' privilege for the 'Resource Requirement Detail' entity, which is strictly required for the Resource Scheduling module to function.

Do I need administrator rights to fix this permission error?

Yes, modifying security roles and granting custom entity permissions in the Power Apps admin center requires active Microsoft Dynamics 365 or Power Apps administrator privileges.

Why does Resource Scheduling need this specific entity permission?

When connecting to Project for the web, the application needs to automatically create requirement detail records in the database to properly allocate and track resources across different project timelines.