Sync Microsoft Project Resource Names with SharePoint Users
Question details
Match Microsoft Project resource names with SharePoint users when synchronizing task assignments.
- Product
- Microsoft Project and SharePoint
- Device & OS
- not provided
- Scenario
- A user is synchronizing Project tasks with a SharePoint list and needs resource names to correspond to users in the Assigned To field.
- Observed behavior
- Assignments may not match SharePoint users when Active Directory display names contain characters such as commas or brackets.
Confirm that your Project and SharePoint setup supports task synchronization, and identify an affected resource and its corresponding SharePoint user. Arrange a nonproduction task list for testing and consult your directory administrator before requesting any account-name changes.
Test an approved resource name or display-name change
Use this approach to check whether an approved name without the problematic characters can be matched during synchronization.
This may be a product limitation rather than a configuration error. An alias or display-name change is not guaranteed to resolve the user in SharePoint.
In Microsoft Project, open the affected plan and select View > Resource Sheet. Find the affected resource and compare its name with the user shown in the SharePoint task list.
In a test plan, edit the resource name in the Resource Sheet to an approved alias or another name agreed with your administrator. Synchronize the test plan with a nonproduction SharePoint list and check whether the Assigned To field resolves to the intended user.
If the alias does not resolve, ask your directory administrator whether changing the user's Active Directory display name to remove the problematic characters is permitted. If a change is approved, repeat the synchronization test after the updated name is available in SharePoint.
Test assignment through a SharePoint task item
Use this option when the SharePoint list supports creating or editing tasks directly.
Manage Project-Related Documents with WPS Office
WPS Office is a free, lightweight alternative for working with project documents and spreadsheets in a familiar interface. Its Microsoft Office format compatibility helps make moving everyday files straightforward. It does not fix Microsoft Project–SharePoint synchronization or replace Microsoft Project.

Frequently Asked Questions
Why does a Project resource not match a SharePoint user?
The resource name and the user resolved in SharePoint's Assigned To field may not match. Display names containing characters such as commas or brackets can contribute to this limitation in some setups.
Will using an alias always fix the assignment?
No. SharePoint may not recognize an alias as the intended user. Test the approved alias in Project's View > Resource Sheet and check the assignment after synchronizing with a nonproduction list.
Can I assign the user directly in SharePoint?
Where the list supports it, select New or New Item and choose the user in Assigned To. This tests SharePoint user resolution, but it does not guarantee that Project will synchronize the assignment correctly.
What if I cannot change Active Directory display names?
Test an approved alias or direct SharePoint assignment without changing directory names. If neither works, contact Microsoft support or submit product feedback, because the limitation may not have a direct workaround.