Fix Missing Year in Microsoft Project Resource Chart

Bushra ParveenBushra Parveen Nov 4, 2026 871 views

Question details

The user needs to resolve an issue where the Resource Chart timeline skips a year while the Gantt Chart timeline displays normally.

Fix a Missing Year in the Microsoft Project Resource Chart
Product
Microsoft Project
Device & OS
not provided
Scenario
Reviewing project timelines, resource allocations, and charts within Microsoft Project.
Observed behavior
The Resource Chart timeline appears to skip a year entirely, creating a visual discrepancy with the correct Gantt Chart timeline.
Before you start

Ensure you have your Microsoft Project file open and verify that the Gantt chart timeline is displaying correctly before adjusting global schedule options.

Solution 1Recommended

Adjust the Fiscal Year Starting Month

Realign the Resource Chart timeline by correcting the project's global fiscal year start date.

A fiscal year that begins in a month other than January (such as July) can cause the Resource Chart timeline to appear as if it skips a year, even when the Gantt Chart remains accurate. Resetting the fiscal year to January usually resolves this display discrepancy.

1
Open Project Options

Click on the 'File' tab in the top-left corner of Microsoft Project and select 'Options' at the bottom of the navigation menu.

2
Navigate to Schedule Settings

In the Project Options dialog box, click on the 'Schedule' tab located on the left-hand sidebar.

3
Change the Fiscal Year Start

Locate the 'Fiscal year starts in' dropdown menu under the calendar options and change the setting to 'January'.

4
Apply and Verify

Click 'OK' to apply the changes, then navigate back to your Resource Chart to confirm the timeline no longer skips a year.

Adjust the Fiscal Year Starting Month
Timeline Restored: The Resource Chart and Gantt Chart timelines should now be properly synchronized without any missing periods.
Free Microsoft Office alternative

Manage Project Timelines Seamlessly with WPS Office

While Microsoft Project is a dedicated scheduling tool, it can be expensive and complex. WPS Office provides a free, lightweight, and highly compatible alternative. With built-in Gantt chart templates in WPS Spreadsheet, you can easily track project resources and timelines without the steep learning curve or high software costs.

Completely free to use with a lightweight installation packageHighly compatible with Microsoft Office formats like XLSX, DOCX, and PPTXRich selection of free project management and Gantt chart templatesFamiliar user interface for seamless migration and quick onboarding
microsoft office alternative - wps office

Frequently Asked Questions

Why does changing the fiscal year affect the Resource Chart differently than the Gantt Chart?

Microsoft Project calculates and displays timelines based on global calendar settings. Specific views like the Resource Chart often inherit fiscal year settings more strictly than the standard Gantt Chart, causing visual shifts or skipped years when the fiscal year doesn't start in January.

Will changing the fiscal year start month alter my actual project task dates?

No. Changing the fiscal year start month primarily affects how financial periods are labeled and displayed in timelines and reports. It does not modify the actual scheduled start and finish dates of your project tasks.

Can I set a custom fiscal year for individual resources in MS Project?

No, the fiscal year setting in Microsoft Project is a global option. It applies to the entire project file and cannot be configured independently for individual resources or specific charts.