How to Set a July Fiscal Year for Quarters on a Microsoft Project Gantt Chart
Question details
The user needs to configure a Microsoft Project Gantt chart to display Quarter 1 starting in July, aligning with a July 1 to June 30 fiscal year.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Customizing project timelines to match an organizational fiscal calendar.
- Observed behavior
- The Gantt chart timescale currently labels Quarter 1 as January through March by default, instead of the required July through September.
Ensure you have your Microsoft Project file open and verify the exact start month of your organization's fiscal year before adjusting the timeline settings.
Configure Schedule Options and Timescale for a July Fiscal Year
Adjust the global schedule settings to start the fiscal year in July, then format the Gantt chart timescale to reflect these changes.
Microsoft Project uses a standard calendar year by default. To align your project schedule with a custom fiscal year, you must first change the application's schedule settings and then update the timescale visual labels.
In Microsoft Project, click on the 'File' tab in the top ribbon, select 'Options', and then navigate to the 'Schedule' tab on the left sidebar.
Locate the 'Fiscal Year Starts In' dropdown menu and change the selection from January to 'July'. Click 'OK' to apply the setting.
Return to your Gantt Chart view and double-click directly on the timescale header located at the top of the chart area.
In the Timescale dialog box, navigate to the 'Middle Tier' tab (or the specific tier you wish to adjust). Set the 'Units' to 'Quarters', choose your preferred formatting in the 'Label' dropdown, and click 'OK'.

Manage Your Projects Efficiently with WPS Office
While Microsoft Project requires a dedicated premium license, WPS Office offers a free, lightweight, and comprehensive suite. You can easily build, track, and share customized Gantt charts using professional templates within WPS Spreadsheet.
- 1. Download WPS Office: Install the free WPS Office suite on your computer.
- 2. Open Spreadsheet Templates: Launch WPS Spreadsheet and navigate to the Template library.
- 3. Search for Gantt Chart: Type 'Gantt Chart' in the search bar to find and use ready-made project tracking templates.

Frequently Asked Questions
Can I set a custom fiscal year for a specific project without affecting others in Microsoft Project?
Yes, the 'Fiscal Year Starts In' setting under File > Options > Schedule is applied specifically to the active project by default. Other project files will retain their own individual fiscal year settings.
Why isn't my Gantt chart timescale showing the new fiscal quarters after I changed the start month?
Changing the start month only updates the underlying calendar logic. You must also update the visual display by double-clicking the timescale, navigating to the active tier (e.g., Middle Tier), and explicitly setting the 'Units' to 'Quarters'.
Can I change the fiscal year to start in a month other than July?
Absolutely. In the 'Fiscal Year Starts In' dropdown within the Schedule options, you can select any month from January to December to perfectly match your organization's unique financial calendar.