Can Microsoft Project Change Task Duration Automatically From Dependencies?

Rana GarciaRana Garcia Nov 20, 2026 868 views

Question details

The user wants Task A's duration to extend automatically so that it finishes with a linked task.

Can Microsoft Project Change Task Duration Automatically From Dependencies?
Product
Microsoft Project
Device & OS
not provided
Scenario
Task A has a finish-to-finish dependency on Task B and a start constraint.
Observed behavior
Task A retains its original duration and finishes before Task B instead of extending automatically.
Before you start

In the Gantt Chart, check Task A's task mode, dependency, and constraint in Task Information. Note the intended start date and confirm whether Task A must finish exactly when Task B finishes.

Solution 1Recommended

Set Task A's duration or scheduling values

Use this approach when you can define Task A's duration directly or calculate it from assigned work and resource units.

A finish-to-finish dependency controls the relationship between finish dates; it does not by itself increase a task's duration. Constraints and task mode can also affect the resulting schedule.

1
Review the task settings

In Gantt Chart view, double-click Task A. On the Advanced tab of Task Information, review its constraint type and date, and change them if they conflict with the intended schedule.

2
Enter a duration

In the Gantt Chart table, enter the required value in Task A's Duration cell. Alternatively, enter suitable start and finish dates, then check the resulting duration.

3
Use work and resource units if appropriate

To calculate duration from work, assign a resource to Task A using Resource > Assign Resources, then enter its work and units. Check the task type in Task Information > Advanced and verify the calculated duration; resource calendars and scheduling settings affect the result.

Set Task A's duration or scheduling values
Automatic extension: Entering a fixed duration does not make it extend automatically when Task B changes. For a task that spans two linked dates, consider a hammock task.
Free Microsoft Office alternative

Track project dates in a WPS Spreadsheets worksheet

WPS Office is a free, lightweight alternative with a familiar interface for working with Office documents. Use WPS Spreadsheets to organize project dates in a worksheet, though it does not fix Microsoft Project dependencies or replace its scheduling engine.

Track task start dates, finish dates, and durations in a spreadsheetCompatible with Microsoft Excel XLSX files for easy file sharingFamiliar spreadsheet interface makes migration straightforwardFree and lightweight for everyday document work
microsoft office alternative - wps office

Frequently Asked Questions

Does a finish-to-finish link make two tasks finish on the same date?

Not necessarily. A finish-to-finish link establishes a scheduling relationship but does not by itself extend the successor's duration to match the other task. Check task mode, constraints, calendars, and any lag in Task Information.

How can I check Task A's start constraint?

In Gantt Chart view, double-click Task A and open the Advanced tab in Task Information. Review the constraint type and constraint date there.

What is a hammock task in Microsoft Project?

A hammock task spans between dates linked from other tasks or milestones. For example, you can use Paste Special > Paste Link to link its start to a milestone and its finish to another task.

Can Project calculate duration from resource assignments?

Yes. Project can calculate duration from work and resource units when the task's scheduling settings allow it. Assign a resource through Resource > Assign Resources and review the task type in Task Information > Advanced.