Change a Microsoft Project Task to Auto Scheduled Without Losing Dates
Question details
The user wants to switch a task from manually scheduled to automatically scheduled while preserving its current start and finish dates.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A task has existing dates that the user wants to retain when changing its scheduling mode.
- Observed behavior
- Changing the task to Auto Scheduled causes Project to recalculate its start and finish dates.
In a task view, record the task's current start date and time, finish date and time, and duration. Check its predecessors and task calendar, because these can affect the recalculated dates.
Set a start constraint after switching to Auto Scheduled
Use a start constraint to preserve a required start date while allowing Microsoft Project to calculate the finish date.
A start constraint does not guarantee the original finish date. Project calculates the finish from the start, duration, calendar, dependencies, and other scheduling settings.
In a task view such as Gantt Chart, note the task's Start, Finish, and Duration values. Record the start time as well as the date.
Select the task, then choose Task > Auto Schedule. Project may recalculate its dates immediately.
Double-click the task to open Task Information, then select the Advanced tab.
Under Constraint type, select Must Start On to require the recorded start date, or Start No Earlier Than to allow a later start if scheduling requires it. Enter the recorded start in Constraint date, then select OK.
Compare the task's Start and Finish values with the dates you recorded. If the finish has changed, review Duration, predecessors, and the task calendar before adjusting the schedule.

Use WPS Office for Project-Related Documents and Reports
WPS Office is a free, lightweight alternative for working with project reports, spreadsheets, and presentations. Its familiar interface and Microsoft Office format compatibility make it easy to move existing documents, but it does not change Microsoft Project scheduling or constraints.

Frequently Asked Questions
Why did my task dates change when I selected Auto Schedule?
Microsoft Project recalculates automatically scheduled tasks using factors such as duration, predecessors, calendars, and constraints. Review these settings in the task view and Task Information.
Does Must Start On preserve both the start and finish dates?
No. Must Start On fixes the required start, but Project calculates the finish from the task's duration and schedule settings. Compare the resulting Finish value with the original.
Which start constraint allows the task to move later?
In Task Information > Advanced, select Start No Earlier Than. The task cannot start before the constraint date, but dependencies or other scheduling factors can move it later.
What can I do if both dates must stay exactly as entered?
First review the task's duration, calendar, and dependencies to see whether the dates are compatible with automatic scheduling. If they are not, consider keeping the task manually scheduled.