Fix Incorrect Summary Task Work Completion in Microsoft Project 2016
Question details
Determine why a summary task shows 100% Work Complete when only one subtask is finished.

- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- A project summary task contains multiple subtasks and may also have a resource assigned directly to it.
- Observed behavior
- The summary task can show 100% Work Complete even though some subtasks are not finished.
Identify the affected summary task and its subtasks, and check whether the summary assignment is required for a Team Services integration. Work Complete measures completed work, while % Complete is based on duration.
Review Work Values and Summary Task Assignments
Use this approach to distinguish a valid work-based calculation from an issue caused by a direct summary-task assignment.
In Project, open File > Account > Update Options > Update Now if that option is available. Install any updates and reopen the project.
In the Gantt Chart view, right-click a column heading and choose Insert Column. Add % Work Complete, % Complete, Work, Remaining Work, Actual Duration, and Duration.
Inspect the values on each subtask and the summary. If all planned work belongs to the finished subtask, 100% Work Complete can be correct even when other subtasks remain unfinished.
Select the summary task and open Resource > Assign Resources. If a direct resource assignment is unnecessary, select the resource and choose Remove.
Press F9 to recalculate the project, then review the summary and subtask values again. Check that remaining tasks have the appropriate work and resource assignments.

Track Project Progress in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for maintaining project progress tables. Its Microsoft Office format compatibility makes it easy to move spreadsheet-based tracking into WPS; it does not fix Microsoft Project calculations or replace Project integrations.

Frequently Asked Questions
Why does the summary show 100% Work Complete when tasks remain?
If all planned work is assigned to a finished subtask, the work-based percentage may correctly be 100%. Insert the Work and Remaining Work columns in the Gantt Chart view to compare the subtasks.
How is % Work Complete different from % Complete?
% Work Complete measures completed work against planned work. % Complete is based on duration, so the two values can differ when work and duration are distributed differently.
Should I remove a resource assigned to the summary task?
If the assignment is unnecessary, select the summary task, open Resource > Assign Resources, and remove it. If the summary represents a linked Agile story, check the Team Services integration requirements first.
How do I recalculate the project after changing assignments?
Press F9 in Microsoft Project, then compare the summary's % Work Complete and Remaining Work with the values on its subtasks.