Fix Work Hours Not Rolling Up to Summary Tasks in Microsoft Project 2016
Question details
The user needs work hours entered for subtasks to roll up to their summary task.

- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- A project schedule contains a summary task and subtasks with entered work hours.
- Observed behavior
- Work hours are not rolling up to the summary task because the summary task is linked as a predecessor of one of its own subtasks.
Open the affected project in Microsoft Project 2016 and identify the summary task and its subtasks. Add the Work column in Gantt Chart view if it is not already visible so you can check the rollup.
Remove the dependency between the summary task and its subtask
Use this solution when a summary task is set as a predecessor of one of its own subtasks.
Open View > Gantt Chart, expand the affected summary task, and select the subtask that has the summary task as a predecessor.
Double-click the subtask to open Task Information, select the Predecessors tab, and find the row containing its parent summary task.
Delete the predecessor row for the parent summary task, then select OK. Leave unrelated task links in place.
In Gantt Chart view, compare the Work values on the subtask rows with the summary task's Work value. If the rollup still looks incorrect, review the other task links and resource assignments.

Track project work in WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface. Use WPS Spreadsheets to track task hours in Microsoft Excel-compatible files and move existing Office documents into your workflow. It does not fix Microsoft Project dependencies or replace Project scheduling.

Frequently Asked Questions
Why are work hours not rolling up to my summary task?
An invalid dependency can prevent Project from calculating the schedule correctly. Check whether the summary task is listed as a predecessor of one of its own subtasks in the subtask's Task Information > Predecessors tab.
Where can I see work hours for tasks and summary tasks?
In View > Gantt Chart, add the Work column if it is not visible. Expand the summary task to compare its Work value with the values on its subtask rows.
What should I check if removing the link does not resolve the rollup?
Review the remaining links in the affected tasks' Task Information > Predecessors tabs and check their resource assignments. Also confirm that you are comparing the Work field rather than Duration.
Can WPS Office fix a Microsoft Project dependency?
No. Remove the invalid dependency in Microsoft Project. WPS Spreadsheets can be used separately to track task hours in an XLSX workbook, but it does not replace Project's scheduling features.