The user needs to understand why two Microsoft Project tasks with identical durations calculate different total work hours.

Why Do Microsoft Project Task Work Hours Not Match?
Product
Microsoft Project
Device & OS
not provided
Scenario
Planning or reviewing a project schedule where task durations match but the calculated total work amounts differ unexpectedly.
Observed behavior
Work hour totals diverge between tasks that have the exact same duration, causing confusion in resource or project planning.
Before you start

Verify that your project baseline is not unexpectedly skewing your view, and note down the start and finish dates of the affected tasks before making structural changes.

Solution 1Recommended

Verify Project, Task, and Resource Calendars

Different working hours set across various calendars will cause identical duration tasks to calculate different work totals.

Microsoft Project calculates work based on the specific calendar applied. If one task uses a standard 8-hour day calendar and another is assigned a resource with a 6-hour day calendar, the resulting work hours will differ even if both tasks last for 5 days.

1
Check the Project Calendar

Navigate to the 'Project' tab, click 'Project Information', and check which Base Calendar is applied to the overall project.

2
Verify Task-Specific Calendars

Double-click the specific task to open 'Task Information', go to the 'Advanced' tab, and check if a specific calendar is selected in the 'Calendar' drop-down menu.

3
Confirm Resource Working Times

Go to the 'View' tab, select 'Resource Sheet', and double-click the assigned resource. Check their specific 'Working Time' settings to ensure they match the expected daily hours.

Verify Project, Task, and Resource Calendars
Calendar Priority: Resource calendars generally override the project calendar. If a task calendar is set to 'Scheduling ignores resource calendars', the task calendar takes precedence.
Free Microsoft Office alternative

Plan Projects Efficiently with WPS Office

If you are struggling with complex Microsoft Project calculations and scheduling engines, consider managing your tasks with WPS Spreadsheet. It offers highly customizable Gantt chart templates and full compatibility with Microsoft Excel formats for a simpler, lightweight project management experience.

  1. 1. Open WPS Spreadsheet: Launch WPS Office and click on 'Spreadsheet' to open a new workspace.
  2. 2. Access Project Templates: Click on 'Templates' in the start screen and search for 'Gantt Chart' or 'Project Schedule'.
  3. 3. Customize Your Schedule: Download a free template and start entering your tasks, durations, and resources directly without worrying about hidden scheduling algorithms.
Easily build and customize project schedules and Gantt charts without complex calculation enginesFully compatible with Microsoft Excel (.xlsx) formats for easy sharingLightweight, user-friendly interface that requires minimal trainingFree to use across Windows, Mac, Linux, iOS, and Android devices
microsoft office alternative - wps office

Frequently Asked Questions

How does the 'Effort Driven' setting impact task work?

If a task is Effort Driven, the total work remains constant. When you add new resources to the task, Microsoft Project decreases the duration rather than increasing the total work hours.

Can start and finish dates cause work hour mismatches?

Yes. If a task's duration crosses over weekends, holidays, or non-working days defined in the calendar, the actual working time available changes, which directly affects the total calculated work hours.

Why did my work hours change when I changed a resource?

Work hours recalculate based on the new resource's specific base calendar and their default assignment units. If the new resource works fewer hours per day, the total work for the same task duration will decrease.