Fix Incorrect Timeline Start Dates in Microsoft Project
Question details
Identify why a Microsoft Project timeline shows a different task start date from the Gantt chart.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A task appears to start on Tuesday in the timeline but on Wednesday in the Gantt chart.
- Observed behavior
- The timeline and Gantt chart appear to show different start dates for the same task.
Identify the affected task and compare its Start value in the Gantt Chart with the task shown on the timeline. Note the project calendar and any task calendar assigned to that task.
Check the Project Start Time and Working Calendar
Use this approach when an unexpected start time or working-day setting may be shifting the schedule.
Go to File > Options > General and choose a Date format that includes the time. Return to the Gantt Chart and inspect the affected task's Start value.
Open Project > Project Information and check the Start date and time. If the project is scheduled from its start date and the value is incorrect, enter the intended date and time.
Open Project > Change Working Time and select the project calendar. Check the Exceptions and Work Weeks tabs for unintended working days or extra working hours, then correct any inaccurate entries.
Double-click the affected task in the Gantt Chart and review its Duration, constraint, and calendar settings in Task Information. Correct any unintended duration, constraint, or task calendar.
Press F9 to recalculate the project, then compare the task's Start value in the Gantt Chart with its position on the timeline.
Create a Project Schedule in WPS Spreadsheet
WPS Office is a free, lightweight alternative for working with familiar Microsoft Office documents. Use WPS Spreadsheet to build a simple schedule or timeline from task dates in an Excel workbook; it does not repair Microsoft Project schedules.

Frequently Asked Questions
How do I see the time as well as the date in Microsoft Project?
Go to File > Options > General and select a Date format that includes the time. Then check the Start field in the Gantt Chart and the date in Project > Project Information.
Where can I check for an extra working hour?
Open Project > Change Working Time, select the relevant calendar, and inspect the Exceptions and Work Weeks tabs. Review the working hours for the affected day and remove any unintended entry.
Why did recalculating not change the task date?
Check the task's Task Mode in the Gantt Chart. A manually scheduled task may not move automatically; a constraint or task calendar can also affect its dates. Double-click the task to review its settings.
Can WPS Office fix a Microsoft Project timeline?
No. Correct the project schedule and calendar in Microsoft Project. WPS Spreadsheet can be used separately to create a simple timeline from task data in an Excel workbook.