Fix Microsoft Project Resource Costs for Four-Person Assignments

Elise WilliamsElise Williams Nov 22, 2026 868 views

Question details

The user needs Microsoft Project to calculate the cost of four people working on a task.

Fix Resource Costs for Four-Person Assignments in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A resource represents four people and has Maximum Units set to 400%.
Observed behavior
The task is allocated only eight work hours per day and calculates the cost of one person rather than four.
Before you start

Check each person’s hourly rate and availability, and confirm the task’s duration and work schedule. For example, four people working eight hours each should produce 32 total work hours.

Solution 1Recommended

Assign four individual resources to the task

Use separate resources to calculate each person’s work and cost and to make over-allocations easier to identify.

Maximum Units defines a resource’s available capacity; it does not assign that capacity to a task. Project calculates work-based costs from assigned work and the applicable resource rates.

1
Create the resources

Open View > Resource Sheet and enter a separate Work resource for each of the four people. Set each resource’s Max. Units to 100% and enter the appropriate hourly rate in Std. Rate.

2
Assign all four people

Select the task in Gantt Chart view, then open Resource > Assign Resources. Select the four resources and assign each one at 100%.

3
Check work and cost

Open View > Task Usage and inspect the task’s Work and Cost fields. For a one-day task with eight hours of work per person, check for 32 total work hours and the corresponding sum of the four resource costs.

Assign four individual resources to the task
If adding people should shorten the task: Open Task Information > Advanced and select Fixed Units and Effort Driven. When resources are added to an existing assignment, Project can redistribute the existing work and shorten the duration, subject to calendars and scheduling constraints. Check the resulting work and duration after assigning resources.
Free Microsoft Office alternative

Track Project Resource Estimates in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for creating resource and cost estimates in spreadsheets. Its Microsoft Office format compatibility helps you move existing documents into your workflow. It does not fix Microsoft Project resource assignments.

Estimate resource work and costs in WPS SpreadsheetsOpen and edit Microsoft Excel XLSX filesUse a familiar, easy-to-navigate office interfaceWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does 400% Maximum Units still show only eight hours of work?

Max. Units sets available capacity, not the units assigned to a task. Check the assignment in Resource > Assign Resources; a 100% assignment can represent one person working eight hours on an eight-hour day.

How does Microsoft Project calculate resource cost?

For a work resource, Project calculates work-based cost from assigned work and the applicable resource rate. Enter or check the hourly rate in View > Resource Sheet under Std. Rate, then review Work and Cost in Task Usage.

Can I use different hourly rates for the four people?

Yes. Create separate resources in View > Resource Sheet, enter each person’s Std. Rate, and assign the appropriate people to the task through Resource > Assign Resources.

Will adding four resources automatically shorten the task?

Not necessarily. In Task Information > Advanced, Fixed Units and Effort Driven can cause existing work to be redistributed when resources are added, but calendars and scheduling constraints also affect the result. Check the task’s work and duration afterward.

Can WPS Office fix a Microsoft Project assignment?

No. Change the assignment units and rates in Microsoft Project. WPS Spreadsheets can be used separately to prepare or review resource cost estimates in an Excel-compatible spreadsheet.