Fix Microsoft Project Resource Costs for Four-Person Assignments
Question details
The user needs Microsoft Project to calculate the cost of four people working on a task.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A resource represents four people and has Maximum Units set to 400%.
- Observed behavior
- The task is allocated only eight work hours per day and calculates the cost of one person rather than four.
Check each person’s hourly rate and availability, and confirm the task’s duration and work schedule. For example, four people working eight hours each should produce 32 total work hours.
Assign four individual resources to the task
Use separate resources to calculate each person’s work and cost and to make over-allocations easier to identify.
Maximum Units defines a resource’s available capacity; it does not assign that capacity to a task. Project calculates work-based costs from assigned work and the applicable resource rates.
Open View > Resource Sheet and enter a separate Work resource for each of the four people. Set each resource’s Max. Units to 100% and enter the appropriate hourly rate in Std. Rate.
Select the task in Gantt Chart view, then open Resource > Assign Resources. Select the four resources and assign each one at 100%.
Open View > Task Usage and inspect the task’s Work and Cost fields. For a one-day task with eight hours of work per person, check for 32 total work hours and the corresponding sum of the four resource costs.

Assign a four-person group at 400% units
Use a single group resource when all four people can be represented by the same hourly rate and individual tracking is not needed.
Track Project Resource Estimates in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for creating resource and cost estimates in spreadsheets. Its Microsoft Office format compatibility helps you move existing documents into your workflow. It does not fix Microsoft Project resource assignments.

Frequently Asked Questions
Why does 400% Maximum Units still show only eight hours of work?
Max. Units sets available capacity, not the units assigned to a task. Check the assignment in Resource > Assign Resources; a 100% assignment can represent one person working eight hours on an eight-hour day.
How does Microsoft Project calculate resource cost?
For a work resource, Project calculates work-based cost from assigned work and the applicable resource rate. Enter or check the hourly rate in View > Resource Sheet under Std. Rate, then review Work and Cost in Task Usage.
Can I use different hourly rates for the four people?
Yes. Create separate resources in View > Resource Sheet, enter each person’s Std. Rate, and assign the appropriate people to the task through Resource > Assign Resources.
Will adding four resources automatically shorten the task?
Not necessarily. In Task Information > Advanced, Fixed Units and Effort Driven can cause existing work to be redistributed when resources are added, but calendars and scheduling constraints also affect the result. Check the task’s work and duration afterward.
Can WPS Office fix a Microsoft Project assignment?
No. Change the assignment units and rates in Microsoft Project. WPS Spreadsheets can be used separately to prepare or review resource cost estimates in an Excel-compatible spreadsheet.