Why Microsoft Project Costs Do Not Match Resource Usage Costs

Amos GikundaAmos Gikunda Nov 27, 2026 868 views

Question details

The user wants to understand why the Project Summary Task cost differs from the total in Resource Usage.

Why Microsoft Project Costs Do Not Match Resource Usage Costs
Product
Microsoft Project
Device & OS
not provided
Scenario
Comparing the overall project cost with resource-based costs in the Resource Usage view.
Observed behavior
The Project Summary Task cost differs from the total shown in Resource Usage; task fixed costs may account for the difference.
Before you start

Open the project in Microsoft Project and compare the Project Summary Task cost with the total in Resource Usage. Check that the Resource Usage view is not filtered in a way that excludes resources.

Solution 1Recommended

Check task fixed costs in the Gantt Chart

Use this method to find fixed costs included in the project total but not assigned to resources.

Fixed costs entered directly on tasks contribute to task and project totals, but they are not resource costs and therefore do not appear as resource costs in Resource Usage.

1
Open the Gantt Chart

In Microsoft Project, select View > Gantt Chart.

2
Add the Fixed Cost column

Right-click a column heading, select Insert Column, and choose Fixed Cost.

3
Review task values

Inspect the Fixed Cost column for nonzero values, including any on summary tasks. If needed, select Format > Project Summary Task to display the project-level row.

4
Correct unintended costs

Select any incorrect Fixed Cost cell and enter the intended amount, or enter 0 if the cost was added unintentionally. Keep fixed costs that are valid project expenses.

5
Compare the totals again

Check the Project Summary Task cost, then select View > Resource Usage and compare the totals. If they still differ, review the visible resources and other cost entries.

Check task fixed costs in the Gantt Chart
A difference can be expected: The totals do not need to match when the project legitimately includes fixed costs that are not assigned to resources.
Free Microsoft Office alternative

Track project cost summaries with WPS Spreadsheets

WPS Office is a free, lightweight Office alternative with a familiar interface for working with project cost spreadsheets. Its Microsoft Office format compatibility makes it easy to move existing documents and spreadsheets into your workflow, though it does not fix Microsoft Project cost calculations.

Organize resource and fixed-cost figures in spreadsheets.Open and edit Microsoft Excel XLSX files for easier migration.Work with a familiar, easy-to-use Office-style interface.Use a free, lightweight suite for everyday documents and spreadsheets.
microsoft office alternative - wps office

Frequently Asked Questions

Why are fixed costs missing from Resource Usage?

Fixed costs entered on tasks are not assigned to resources, so they contribute to task and project totals without appearing as resource costs in Resource Usage.

How do I find fixed costs in Microsoft Project?

Select View > Gantt Chart, right-click a column heading, select Insert Column, and choose Fixed Cost. Review the values on tasks and summary tasks.

Should I remove all fixed costs to make the totals match?

No. In the Gantt Chart's Fixed Cost column, correct or remove only unintended amounts. Valid fixed costs can make the project total legitimately higher than resource-based costs.

How do I display the overall project cost?

In the Gantt Chart, select Format > Project Summary Task to show the project-level row. Add the Cost column if it is not already visible.