Why Microsoft Project Costs Do Not Match Resource Usage Costs
Question details
The user wants to understand why the Project Summary Task cost differs from the total in Resource Usage.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Comparing the overall project cost with resource-based costs in the Resource Usage view.
- Observed behavior
- The Project Summary Task cost differs from the total shown in Resource Usage; task fixed costs may account for the difference.
Open the project in Microsoft Project and compare the Project Summary Task cost with the total in Resource Usage. Check that the Resource Usage view is not filtered in a way that excludes resources.
Check task fixed costs in the Gantt Chart
Use this method to find fixed costs included in the project total but not assigned to resources.
Fixed costs entered directly on tasks contribute to task and project totals, but they are not resource costs and therefore do not appear as resource costs in Resource Usage.
In Microsoft Project, select View > Gantt Chart.
Right-click a column heading, select Insert Column, and choose Fixed Cost.
Inspect the Fixed Cost column for nonzero values, including any on summary tasks. If needed, select Format > Project Summary Task to display the project-level row.
Select any incorrect Fixed Cost cell and enter the intended amount, or enter 0 if the cost was added unintentionally. Keep fixed costs that are valid project expenses.
Check the Project Summary Task cost, then select View > Resource Usage and compare the totals. If they still differ, review the visible resources and other cost entries.

Track project cost summaries with WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface for working with project cost spreadsheets. Its Microsoft Office format compatibility makes it easy to move existing documents and spreadsheets into your workflow, though it does not fix Microsoft Project cost calculations.

Frequently Asked Questions
Why are fixed costs missing from Resource Usage?
Fixed costs entered on tasks are not assigned to resources, so they contribute to task and project totals without appearing as resource costs in Resource Usage.
How do I find fixed costs in Microsoft Project?
Select View > Gantt Chart, right-click a column heading, select Insert Column, and choose Fixed Cost. Review the values on tasks and summary tasks.
Should I remove all fixed costs to make the totals match?
No. In the Gantt Chart's Fixed Cost column, correct or remove only unintended amounts. Valid fixed costs can make the project total legitimately higher than resource-based costs.
How do I display the overall project cost?
In the Gantt Chart, select Format > Project Summary Task to show the project-level row. Add the Cost column if it is not already visible.