Fix Resource Units and Cost Not Updating in Microsoft Project

John WilsonJohn Wilson Nov 25, 2026 868 views

Question details

Correct resource units and update the associated task cost in Microsoft Project.

Fix Resource Units and Cost Not Updating in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A resource assignment should use 1200% units on an eight-week task.
Observed behavior
Changing the resource units from 100% to 1200% does not change the cost as expected.
Before you start

Identify the affected task and its assigned Work resource, and check the intended duration and resource rate. Confirm that the project and resource calendars reflect the expected working time.

Solution 1Recommended

Correct the fixed-duration task and recalculate its resource cost

Use this approach when changing assignment units does not produce the expected work or cost.

1
Open the task details

Go to View > Gantt Chart, select the affected task, and turn on View > Details to display the Task Form pane.

2
Set the task type

Double-click the task, open the Advanced tab in Task Information, and set Task type to Fixed Duration. Click OK.

3
Restore the duration

In the Gantt Chart Duration field, enter the intended eight weeks or 40 working days. Verify the task calendar if the resulting dates are not as expected.

4
Update assignment units

Select the task and enter 1200% in the assigned Work resource's Units field in the Task Form. Click OK in the pane to apply the change.

5
Check the rate and recalculate

Open View > Resource Sheet and check the resource's Standard Rate and other applicable cost settings. Then press F9 to recalculate the project and review the task's Work and Cost fields.

Correct the fixed-duration task and recalculate its resource cost
Check what contributes to the cost: Resource cost depends on calculated work and applicable rates; fixed costs and actual costs may be handled separately. Keep the resource type as Work—changing it to Material does not correct the task settings.
Free Microsoft Office alternative

Review exported project costs in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for reviewing project data exported to Excel. It supports an easy transition for spreadsheet work, but it does not fix Microsoft Project scheduling or recalculate native project assignments.

Review exported resource units, work, and cost data in a spreadsheetOpen and edit Microsoft Excel XLSX and XLS filesUse a familiar spreadsheet interface for an easy transitionWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

What does 1200% resource units mean?

For a Work resource, 1200% represents assignment capacity equivalent to 12 full-time units. The actual work and cost also depend on the task duration, calendars, and resource rates.

Why is the cost still unchanged after I update the units?

Check the task's Work field and the resource's Standard Rate in View > Resource Sheet. Also review fixed and actual costs, then press F9 to recalculate the project.

Should I change the resource from Work to Material?

No. Keep it as a Work resource when tracking time-based work and labor cost. Correct the task type, duration, units, and rate instead.

Is eight weeks always the same as 40 working days?

It is 40 working days under a five-day workweek. Check the project, task, and resource calendars if working days or hours differ from that assumption.

Can WPS Office recalculate my Microsoft Project schedule?

No. Make scheduling and assignment changes in Microsoft Project. You can export project data to an Excel file and review that data in WPS Spreadsheets.