Fix Resource Units and Cost Not Updating in Microsoft Project
Question details
Correct resource units and update the associated task cost in Microsoft Project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A resource assignment should use 1200% units on an eight-week task.
- Observed behavior
- Changing the resource units from 100% to 1200% does not change the cost as expected.
Identify the affected task and its assigned Work resource, and check the intended duration and resource rate. Confirm that the project and resource calendars reflect the expected working time.
Correct the fixed-duration task and recalculate its resource cost
Use this approach when changing assignment units does not produce the expected work or cost.
Go to View > Gantt Chart, select the affected task, and turn on View > Details to display the Task Form pane.
Double-click the task, open the Advanced tab in Task Information, and set Task type to Fixed Duration. Click OK.
In the Gantt Chart Duration field, enter the intended eight weeks or 40 working days. Verify the task calendar if the resulting dates are not as expected.
Select the task and enter 1200% in the assigned Work resource's Units field in the Task Form. Click OK in the pane to apply the change.
Open View > Resource Sheet and check the resource's Standard Rate and other applicable cost settings. Then press F9 to recalculate the project and review the task's Work and Cost fields.

Review exported project costs in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for reviewing project data exported to Excel. It supports an easy transition for spreadsheet work, but it does not fix Microsoft Project scheduling or recalculate native project assignments.

Frequently Asked Questions
What does 1200% resource units mean?
For a Work resource, 1200% represents assignment capacity equivalent to 12 full-time units. The actual work and cost also depend on the task duration, calendars, and resource rates.
Why is the cost still unchanged after I update the units?
Check the task's Work field and the resource's Standard Rate in View > Resource Sheet. Also review fixed and actual costs, then press F9 to recalculate the project.
Should I change the resource from Work to Material?
No. Keep it as a Work resource when tracking time-based work and labor cost. Correct the task type, duration, units, and rate instead.
Is eight weeks always the same as 40 working days?
It is 40 working days under a five-day workweek. Check the project, task, and resource calendars if working days or hours differ from that assumption.
Can WPS Office recalculate my Microsoft Project schedule?
No. Make scheduling and assignment changes in Microsoft Project. You can export project data to an Excel file and review that data in WPS Spreadsheets.