Fix Microsoft Project Tasks Jumping to 100% Complete
Question details
The user needs to enter a partial completion percentage for Microsoft Project tasks that revert to 100%.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Updating the percent complete of automatically scheduled tasks, including tasks with actual dates or inconsistent duration information.
- Observed behavior
- Some tasks change to 100% complete when a lower nonzero value, such as 30%, is entered.
Open the project in the Microsoft Project desktop client and locate an affected task in the Gantt Chart view. Note its current duration and check whether it has an Actual Finish date.
Reset the task duration before entering percent complete
Use this workaround when a task without an Actual Finish date jumps to 100% after you enter a partial completion value.
In View > Gantt Chart, find the affected task and note the value in its Duration column.
Select the task's Duration cell, enter 1 day, and press Enter.
In the task's % Complete column, enter the intended value, such as 30%, and press Enter.
Enter the original value in the Duration cell, then check the task's % Complete and scheduled dates.

Remove an incorrect Actual Finish date
Use this method if an unfinished task has an Actual Finish date, which makes Microsoft Project treat it as 100% complete.
Track Simple Task Progress in WPS Spreadsheet
WPS Office is a free, lightweight alternative for familiar spreadsheet-based task tracking. Its familiar interface and Microsoft Office format compatibility make it easy to move existing spreadsheets into WPS. It does not fix Microsoft Project scheduling or replace Project's scheduling features.

Frequently Asked Questions
Why does a task with an Actual Finish date show 100% complete?
Microsoft Project treats a task with an Actual Finish date as finished. In Gantt Chart view, insert the Actual Finish column and check whether the date is correct.
How do I enter 30% complete if the task keeps changing to 100%?
If the task has no Actual Finish date, note its Duration, temporarily change it to 1 day, enter 30% in the % Complete column, and restore the original duration.
Should I clear the Actual Finish date on a completed task?
No. Leave the Actual Finish date in place if the task is genuinely finished. Clear it by entering NA only when the date is incorrect and the task is still in progress.
Can WPS Office fix this Microsoft Project scheduling issue?
No. The duration and Actual Finish fixes must be made in Microsoft Project. WPS Spreadsheet can be used separately to track simple task progress in an Excel-compatible workbook.