The user needs to enter a partial completion percentage for Microsoft Project tasks that revert to 100%.

Product
Microsoft Project
Device & OS
not provided
Scenario
Updating the percent complete of automatically scheduled tasks, including tasks with actual dates or inconsistent duration information.
Observed behavior
Some tasks change to 100% complete when a lower nonzero value, such as 30%, is entered.
Before you start

Open the project in the Microsoft Project desktop client and locate an affected task in the Gantt Chart view. Note its current duration and check whether it has an Actual Finish date.

Solution 1Recommended

Reset the task duration before entering percent complete

Use this workaround when a task without an Actual Finish date jumps to 100% after you enter a partial completion value.

1
Record the original duration

In View > Gantt Chart, find the affected task and note the value in its Duration column.

2
Set a temporary duration

Select the task's Duration cell, enter 1 day, and press Enter.

3
Enter the completion percentage

In the task's % Complete column, enter the intended value, such as 30%, and press Enter.

4
Restore the duration

Enter the original value in the Duration cell, then check the task's % Complete and scheduled dates.

Reset the task duration before entering percent complete
Review recalculated values: Changing duration can affect the schedule and calculated progress. If the task still shows 100%, check its Actual Finish date.
Free Microsoft Office alternative

Track Simple Task Progress in WPS Spreadsheet

WPS Office is a free, lightweight alternative for familiar spreadsheet-based task tracking. Its familiar interface and Microsoft Office format compatibility make it easy to move existing spreadsheets into WPS. It does not fix Microsoft Project scheduling or replace Project's scheduling features.

Track task durations and completion percentages in a spreadsheetOpen and edit Microsoft Excel XLSX files for a smoother transitionWork with a familiar, easy-to-use spreadsheet interfaceUse a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does a task with an Actual Finish date show 100% complete?

Microsoft Project treats a task with an Actual Finish date as finished. In Gantt Chart view, insert the Actual Finish column and check whether the date is correct.

How do I enter 30% complete if the task keeps changing to 100%?

If the task has no Actual Finish date, note its Duration, temporarily change it to 1 day, enter 30% in the % Complete column, and restore the original duration.

Should I clear the Actual Finish date on a completed task?

No. Leave the Actual Finish date in place if the task is genuinely finished. Clear it by entering NA only when the date is incorrect and the task is still in progress.

Can WPS Office fix this Microsoft Project scheduling issue?

No. The duration and Actual Finish fixes must be made in Microsoft Project. WPS Spreadsheet can be used separately to track simple task progress in an Excel-compatible workbook.