How to Create a Custom Total Slack Column in Microsoft Project
Question details
The user needs a way to calculate total slack relative to a selected milestone or task instead of the project finish date, as inactivating later tasks is not a viable long-term solution.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Reviewing intermediate project schedules and tracking float or slack for specific milestones without permanently altering the critical path.
- Observed behavior
- Microsoft Project's standard Total Slack field only bases its calculations on the final project schedule and finish date, failing to directly support custom reference points for relative float.
Before applying temporary constraints or altering task relationships, save a backup copy of your project file (.mpp) to ensure you do not permanently disrupt your baseline critical path.
Apply Temporary Constraints to Major Milestones
Use milestone constraints to focus on specific schedule areas during periodic review meetings by forcing slack calculations to be relative to that target milestone.
This constraint method forces Microsoft Project to recalculate total slack based on a specific milestone rather than the project's overall finish date. It is highly effective for periodic schedule reviews.
Double-click the target milestone or task in your Microsoft Project schedule to open the Task Information dialog box.
Navigate to the Advanced tab. Under the Constraint type dropdown menu, select 'Must Finish On' and set the date to match the milestone's target date.
View your schedule. The Total Slack column will now calculate the float for all predecessor tasks relative to this newly constrained milestone.
After concluding your review meeting, reopen the Task Information dialog box and change the Constraint type back to 'As Soon As Possible' to restore standard project logic.

Utilize a Logic-Tracing Add-in
For complex schedules with multiple calendars or recorded progress, use a third-party add-in to calculate relative float along dependency paths.
Track Project Timelines Effectively with WPS Office
While Microsoft Project handles complex dependency networks, WPS Spreadsheet offers an excellent, lightweight alternative for project tracking. You can easily manage schedules, track durations, and visualize timelines using free Gantt chart templates without complex constraint configurations.
- 1. Download and Install WPS Office: Get the free WPS Office suite from the official website and open WPS Spreadsheet.
- 2. Search for Project Templates: Click on 'New' and search for 'Gantt Chart' or 'Project Tracker' in the template library.
- 3. Customize Your Schedule: Input your tasks, start dates, and durations. The template will automatically generate a visual timeline for your project milestones.

Frequently Asked Questions
Why does Microsoft Project calculate Total Slack based only on the project finish date?
Standard Critical Path Method (CPM) logic in Microsoft Project calculates late finish dates by working backward from the final project completion date. Therefore, the standard Total Slack field reflects the float for the entire project network by default.
Can I use custom fields with formulas to calculate relative total slack?
While you can create a custom Number or Duration field, capturing dynamic relative paths with a simple formula is very difficult. Standard formulas cannot automatically trace complex network logic paths to a specific milestone without advanced VBA scripting.
Is it safe to inactivate later tasks to check slack for an intermediate milestone?
Inactivating successor tasks will force the software to recalculate slack for the remaining active network. However, this is not a practical long-term solution because it heavily alters your schedule structure and creates a high risk of accidentally omitting tasks when it's time to reactivate them.