Others

View Monthly Planned Work Totals in Microsoft Project 2013

Natalie TaylorNatalie Taylor Nov 13, 2026 868 views

Question details

The user needs total planned work hours for all tasks grouped by month, with an option to export the results to Excel.

View Monthly Planned Work Totals in Microsoft Project 2013
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
Review project-wide work by month and optionally analyze the timephased totals in Excel.
Observed behavior
Monthly work totals are displayed for the project as a whole and can be exported for spreadsheet analysis.
Before you start

Open the project schedule and check that its tasks have work values. Decide whether you need current scheduled Work or saved Baseline Work, since they can differ.

Solution 1Recommended

Show monthly work totals in Task Usage

Use the project summary row to see scheduled work for all tasks by month.

1
Open Task Usage

In Microsoft Project 2013, select View > Task Usage.

2
Show the project summary

On the Format tab, select Project Summary Task. The project summary row appears at the top of the task list.

3
Set the timescale to months

Right-click the timescale above the right-hand grid, select Timescale, and set the displayed tier's Units to Months.

4
Display work hours

On the Format tab, select Work in the Details group. Read the monthly totals across the project summary row.

Show monthly work totals in Task Usage
Scheduled work versus baseline: Work represents the current scheduled work, which can change as the project is updated. To compare it with the original plan, display Baseline Work instead, provided a baseline has been saved.
Free Microsoft Office alternative

Analyze exported project work totals in WPS Spreadsheets

WPS Office is a free, lightweight Office alternative with a familiar interface. Open an Excel report exported from Microsoft Project in WPS Spreadsheets to continue reviewing monthly work data and make migration between Office formats easier.

Review exported monthly work totals in a spreadsheet.Open and edit Microsoft Excel XLSX files.Use a familiar spreadsheet interface for everyday analysis.Work with a free, lightweight Office suite.
microsoft office alternative - wps office

Frequently Asked Questions

Where can I see the total work for the whole project?

Select View > Task Usage, then enable Project Summary Task on the Format tab. The summary row shows project-wide values in the timephased grid.

How do I change the work display from days or weeks to months?

In Task Usage, right-click the timescale above the grid, select Timescale, and set the displayed tier's Units to Months.

Can I see a running total of work?

In Task Usage, use Format > Details > Add Details to add Cumulative Work to the timephased grid. This shows a running total rather than each month's separate work value.

Does the Work field show the original plan?

Not necessarily. Work reflects the current schedule. If you saved a baseline, add Baseline Work to the usage view to inspect the saved plan.

Can I export the monthly totals without writing a macro?

Yes. Select Report > Visual Reports and generate an Excel report using Task Usage data. Arrange the Work and time fields in the resulting PivotTable to show monthly totals.