Fix Microsoft Project Duration That Does Not Match Start and Finish Dates
Question details
Understand why a task's Duration can differ from the calendar span between its Start and Finish dates.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A task is assigned to a resource whose calendar has shorter working days than the project's standard hours-per-day setting.
- Observed behavior
- The task spans more calendar days than its displayed Duration suggests.
Identify the affected task and its assigned resources. Check whether the task is automatically scheduled and whether other resources or task constraints could affect its dates.
Check Project's Duration Settings and Resource Calendar
Use this method to explain a duration mismatch caused by shorter resource workdays and verify the task's schedule.
Project uses its hours-per-day setting to convert scheduled duration hours into displayed days; it does not redefine a day for each resource calendar. A resource calendar determines when that resource can work.
For example, 16 scheduled working hours can appear as two days when the hours-per-day setting is eight, even if those hours occur over four dates with four working hours each.
Open File > Options > Schedule and review the Hours per day setting. Changing this conversion setting does not change the working hours on a calendar.
Open Project > Change Working Time, select the resource's calendar in the For calendar list, and review its work weeks and exceptions. Confirm the working hours match the resource's actual availability.
Open View > Task Usage and find the task and its resource assignments. Check the assignment units and scheduled work, especially if multiple resources are assigned.
In a task view, use Add New Column to display Start, Finish, Duration, and Work. Compare the dates and work with the resource calendar rather than treating displayed duration days as elapsed calendar days.

Track Project Dates and Work in WPS Spreadsheet
WPS Office is a free, lightweight alternative with a familiar interface for reviewing project dates and work in spreadsheets. Open compatible Microsoft Office files to make migration straightforward; WPS does not change Microsoft Project's scheduling calculations.

Frequently Asked Questions
Why does a two-day task span four dates in Microsoft Project?
If the task has 16 scheduled working hours and Project uses eight hours per day, Duration can display two days. A resource calendar limited to four hours per date can spread that work across four dates.
Where can I check Project's hours-per-day setting?
Open File > Options > Schedule and look for Hours per day. This setting converts duration hours into displayed days; it does not set the calendar's working hours.
Is a four-hour workday the same as assigning a resource at 50%?
No. A four-hour calendar limits when the resource can work, while 50% units specify the assignment level. Review the resource calendar under Project > Change Working Time and the assignment units in View > Task Usage.
Which fields should I share when the duration is confusing?
Show Start, Finish, and Work alongside Duration. In a task view, use Add New Column to add these fields so readers can see the scheduled dates and work.