Question details

The user wants to understand why durations and lags expressed in months do not match calendar-month dates in Microsoft Project.

Why Microsoft Project Durations Do Not Match Calendar Dates
Product
Microsoft Project
Device & OS
not provided
Scenario
A project schedule uses month-based activity durations and dependency lags.
Observed behavior
A 13-month activity finishes in less than 12 calendar months, and a 10-month lag spans about 9.5 calendar months.
Before you start

Open the project and identify a task or dependency whose dates differ from your expectations. Check its duration or lag, start and finish dates, and any assigned resources.

Solution 1Recommended

Check the Project month conversion and working calendars

Use this approach to identify why a duration in months spans a different number of calendar months.

By default, Microsoft Project converts one month to 20 working days. Actual calendar months have different numbers of working days, and working-time calendars affect when those days can be scheduled.

1
Review the month conversion

Open File > Options > Schedule and check Days per month and Hours per day under the calendar options for the project. With the default settings, 13 months represents 260 working days, not 13 calendar months.

2
Check the project calendar

Open Project > Project Information and check the Calendar setting. Then select Project > Change Working Time to review working days, hours, and exceptions such as holidays.

3
Inspect task and resource calendars

Open the affected task's Task Information dialog and check the calendar on the Advanced tab. If resources are assigned, review their working time through Project > Change Working Time as well.

Check the Project month conversion and working calendars
Changing the conversion is not a calendar-month fix: Days per month controls how Project converts duration units; it does not make every month-long duration end on the same date in the next calendar month.
Free Microsoft Office alternative

Review project schedule exports in WPS Spreadsheet

WPS Office is a free, lightweight alternative for reviewing project data exported to a spreadsheet. Its familiar interface and Microsoft Office format compatibility make it easy to move between tools. It does not replace Microsoft Project's scheduling engine or fix Project calendar calculations.

Review exported task dates and durations in WPS SpreadsheetOpen and edit Microsoft Excel XLSX filesUse a familiar spreadsheet interface for easier migrationWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does a 13-month task finish in less than 13 calendar months?

By default, Project converts 13 months to 260 working days. The finish date depends on the applicable working calendars, so it will not necessarily be 13 calendar months after the start date.

Where can I check how many days Project uses for a month?

Open File > Options > Schedule and look for Days per month in the calendar options. The default is 20 working days.

Why does a month-based lag not match calendar months?

Project converts the lag to working time rather than counting calendar-month labels. Check the lag in the successor task's Task Information > Predecessors tab and review the applicable working calendar.

Will changing durations to days produce true calendar-month dates?

No. Days and weeks make working-time estimates clearer, but they do not represent variable-length calendar months. A custom field or macro may be needed to calculate calendar-duration intervals.