Why Microsoft Project Duration Does Not Match Working Days
Question details
Determine why a Microsoft Project task duration differs from the expected number of working days.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project uses a six-day workweek, and the user wants task durations to reflect the intended working schedule.
- Observed behavior
- The displayed duration does not match the expected count of working days between the start and finish dates.
Identify the affected task, its start and finish dates, and the calendar it is expected to follow. Confirm the intended working hours for each day, including breaks, holidays, and Sundays.
Align Hours per Day With the Working-Time Calendar
Use this approach when a displayed duration differs from the number of working days you expect.
Microsoft Project calculates duration from working time and uses the Hours per day setting to express that time in days. If a calendar has more or fewer working hours per day than the conversion setting, the displayed duration can differ from a simple count of work dates.
Open File > Options > Schedule and check Hours per day. Set it to the number of working hours you intend Project to use when expressing durations in days.
Open Project > Change Working Time, select the relevant calendar, and review the Work Weeks and Exceptions tabs. Check Monday through Saturday, including start times, finish times, and breaks, and confirm that Sundays and holidays are nonworking when intended.
Open File > Options > Display and choose a date format that includes time. Then inspect the Start and Finish fields for partial working days or unexpected times.
In the task table, inspect the Task Mode column to see whether the task is manually or automatically scheduled. Review the task's dates and duration accordingly.

Check the Project and Task Calendars Used by Summary Tasks
Use this check when a summary task differs from its subtasks or the subtasks use individual task calendars.
Track Project Dates in WPS Spreadsheets
WPS Office is a free, lightweight, easy-to-use alternative for reviewing project schedules in spreadsheets. Its familiar interface and Microsoft Office format compatibility make it easy to move existing files, although it does not fix Microsoft Project calendar settings.

Frequently Asked Questions
Why does a task show more duration days than working dates?
The calendar may have more working hours per day than the Hours per day conversion setting. Compare File > Options > Schedule with the daily hours under Project > Change Working Time.
How do I include Saturdays in the project schedule?
Open Project > Change Working Time, select the relevant calendar, and edit its work week so Saturday has the intended working hours. Check the Exceptions tab for dates that should remain nonworking.
Why is a summary task duration different from its subtasks?
A summary task without a specific task calendar uses the project calendar, while subtasks may use different task calendars. Check Project > Project Information and the Advanced tab in each task's Task Information dialog.
How can I see whether a task starts or finishes partway through a day?
Go to File > Options > Display and select a date format that includes time. Then review the task's Start and Finish fields.