Question details

Determine why a Microsoft Project task duration differs from the expected number of working days.

Why Microsoft Project Duration Does Not Match Working Days
Product
Microsoft Project
Device & OS
not provided
Scenario
A project uses a six-day workweek, and the user wants task durations to reflect the intended working schedule.
Observed behavior
The displayed duration does not match the expected count of working days between the start and finish dates.
Before you start

Identify the affected task, its start and finish dates, and the calendar it is expected to follow. Confirm the intended working hours for each day, including breaks, holidays, and Sundays.

Solution 1Recommended

Align Hours per Day With the Working-Time Calendar

Use this approach when a displayed duration differs from the number of working days you expect.

Microsoft Project calculates duration from working time and uses the Hours per day setting to express that time in days. If a calendar has more or fewer working hours per day than the conversion setting, the displayed duration can differ from a simple count of work dates.

1
Check the day conversion

Open File > Options > Schedule and check Hours per day. Set it to the number of working hours you intend Project to use when expressing durations in days.

2
Review working hours

Open Project > Change Working Time, select the relevant calendar, and review the Work Weeks and Exceptions tabs. Check Monday through Saturday, including start times, finish times, and breaks, and confirm that Sundays and holidays are nonworking when intended.

3
Display task times

Open File > Options > Display and choose a date format that includes time. Then inspect the Start and Finish fields for partial working days or unexpected times.

4
Check the scheduling mode

In the task table, inspect the Task Mode column to see whether the task is manually or automatically scheduled. Review the task's dates and duration accordingly.

Align Hours per Day With the Working-Time Calendar
Count working dates carefully: With Monday through Saturday working and no holidays, December 3 through December 24, 2016, contains 19 working dates, not 18. Actual task duration also depends on the working hours and task start and finish times.
Free Microsoft Office alternative

Track Project Dates in WPS Spreadsheets

WPS Office is a free, lightweight, easy-to-use alternative for reviewing project schedules in spreadsheets. Its familiar interface and Microsoft Office format compatibility make it easy to move existing files, although it does not fix Microsoft Project calendar settings.

Review project dates and working-day calculations in WPS SpreadsheetsOpen and edit Microsoft Excel formats such as XLSX and XLSUse a familiar spreadsheet interface for easier migrationWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does a task show more duration days than working dates?

The calendar may have more working hours per day than the Hours per day conversion setting. Compare File > Options > Schedule with the daily hours under Project > Change Working Time.

How do I include Saturdays in the project schedule?

Open Project > Change Working Time, select the relevant calendar, and edit its work week so Saturday has the intended working hours. Check the Exceptions tab for dates that should remain nonworking.

Why is a summary task duration different from its subtasks?

A summary task without a specific task calendar uses the project calendar, while subtasks may use different task calendars. Check Project > Project Information and the Advanced tab in each task's Task Information dialog.

How can I see whether a task starts or finishes partway through a day?

Go to File > Options > Display and select a date format that includes time. Then review the task's Start and Finish fields.