The user needs to know how to properly schedule a task when zero work occurs on the first planned day in Microsoft Project.

How to Handle Zero Actual Work on the First Day in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Updating task progress when a scheduled task hasn't started on its planned first day.
Observed behavior
Entering a zero in the Actual Work field for the first day does not postpone the planned work or adjust the task's finish date.
Before you start

Ensure you have established the correct project status date before updating task progress to guarantee accurate rescheduling of incomplete work.

Solution 1Recommended

Update the Actual Start Date and Duration

Use this method to explicitly tell Project when the task actually started and how much work remains, ensuring the schedule shifts appropriately.

A zero actual-work entry does not establish an actual start date or give Project enough information to automatically reschedule the remaining work.

1
Adjust Unstarted Tasks

If the task has not started at all, leave it as unstarted and manually move its planned start date to the appropriate new date based on your status date.

2
Enter Actual Start Date

If the task started later than originally planned, input the actual start date and the actual duration of the work performed so far.

3
Update Remaining Work

Adjust the remaining work and duration fields. Microsoft Project will now correctly recalculate the finish date.

Free Microsoft Office alternative

Manage Your Projects Efficiently with WPS Office

While Microsoft Project is used for complex scheduling, you can easily track tasks, actual work, and timelines using free Gantt chart templates in WPS Spreadsheet—a lightweight and highly compatible alternative to Microsoft Office.

  1. 1. Download and Install WPS Office: Get the free WPS Office suite and launch WPS Spreadsheet.
  2. 2. Select a Project Template: Browse the template library for Gantt charts or project trackers to quickly set up your timeline.
  3. 3. Track Task Progress: Easily input actual work, adjust dates, and visualize your project status with high compatibility.
Free, lightweight, and easy-to-use Office suiteFully compatible with Microsoft Excel (.xlsx) formatsAccess hundreds of free project management templatesFamiliar interface for seamless transition from Microsoft Office
microsoft office alternative - wps office

Frequently Asked Questions

Why did older versions of Microsoft Project behave differently with zero actual work?

Earlier versions of Microsoft Project allowed users to enter zero hours on the first day and automatically moved the incomplete work to the right. Microsoft updated the scheduling engine in later versions, requiring explicit start dates or deferred work entries to adjust the timeline.

Can I manually enter deferred work on a specific date in Microsoft Project?

Yes, you can manually enter deferred work by using the Task Usage or Resource Usage views. Simply locate the specific date in the timephased grid and input the work hours manually.

How does the status date affect task rescheduling?

The status date acts as the baseline for updates. When you reschedule incomplete work, Microsoft Project moves the remaining work to start after the status date, ensuring your timeline reflects the current reality of the project.