How to Change the Project Manager Receiving PWA Approval Notifications

Huda QurayshiHuda Qurayshi Oct 15, 2026 869 views

Question details

The user needs to change the recipient of Project Web App (PWA) approval notifications after handing over a project to a new manager.

How to Change the Project Manager Receiving PWA Approval Notifications
Product
Microsoft Project Online
Device & OS
not provided
Scenario
A project has been handed off to a new project manager, but task approval notifications are still being routed to the original project creator.
Observed behavior
Changing PWA administrator permissions or summary-task owners does not redirect team-member task notifications, and attempting to change the status manager from the original creator's client reverts the assignment.
Before you start

Ensure that the new project manager has the necessary PWA permissions to access, check out, and edit the project files using the Microsoft Project desktop client.

Solution 1Recommended

Update the Status Manager for All Detailed Tasks

Approval notifications are driven by the Status Manager assigned to detailed tasks. The new project manager must manually update this field for all tasks within the Microsoft Project client.

Project Online task notifications do not follow overall PWA administrator permissions or summary-task assignments. They are strictly tied to the Status Manager field on individual detailed tasks. To prevent the system from automatically reverting the change, the new project manager must perform this update from their own Microsoft Project client.

1
Open and check out the project

The new project manager must launch the Microsoft Project desktop client, open the target project, and check it out for editing.

2
Apply the Gantt Chart view

Navigate to the View tab and select 'Gantt Chart' to ensure you can see the detailed task list.

3
Insert the Status Manager column

Right-click on any existing column header, select 'Insert Column', and type 'Status Manager' to add it to your view temporarily.

4
Reassign the Status Manager

Click the Status Manager cell for the first detailed task and select the new project manager's name from the drop-down list.

5
Apply to all tasks

Click and hold the fill handle (the small square at the bottom-right corner of the selected cell) and drag it down to apply the new name to every task in the project.

6
Save and publish

Hide the Status Manager column to clean up the view, then save the project and click 'Publish' to push the changes to PWA.

Update the Status Manager for All Detailed Tasks
Perform using the new manager's account: If the original project creator attempts to assign the tasks to the new manager from their own drop-down list, the system may immediately switch it back. This action must be performed by the new project manager.
Free Microsoft Office alternative

Manage Projects Efficiently with WPS Office

While Microsoft Project offers complex enterprise routing like PWA notifications, it can be overwhelming for standard task tracking. If you are looking for an easier way to manage tasks, WPS Office provides a free, lightweight alternative. Use WPS Spreadsheet to instantly build Gantt charts, assign team tasks, and track project statuses without the steep learning curve.

Fully compatible with Microsoft Excel (.xlsx) formats for seamless sharing of project trackers.Access hundreds of free, ready-to-use project management and Gantt chart templates.Lightweight suite that runs smoothly on Windows, Mac, Linux, and mobile devices.Familiar user interface makes it incredibly easy to learn and adopt.
microsoft office alternative - wps office

Frequently Asked Questions

Why do approval notifications still go to the old manager after changing PWA permissions?

PWA approval notifications are tied directly to the 'Status Manager' field on individual detailed tasks, not the overarching project owner or PWA administrator settings. You must explicitly update the tasks themselves to redirect notifications.

Can I change the Status Manager for summary tasks only?

No. Updating the Status Manager on summary tasks does not control the notifications for team-member task assignments. The Status Manager must be updated for every single detailed task in the project.

Why does the Status Manager revert to my name when I try to select someone else?

This typically occurs if you try to reassign the tasks from your own Microsoft Project client. To resolve this, the new project manager needs to log in, open the project, check it out, and change the Status Manager to their own name.